Rate analysis
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.
DSR rate₹260.30per cum
All kinds of soil.
- Item code
- 2.8.1
- Sub-head
- SH 2 · EARTH WORK
- Unit
- cum
- Source row
- 213
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 cum. | |||||
| MACHINERY | |||||
| 0020 | Hydraulic Excavator (3D) with driver and fuel. | day | 0.12 | ₹7,850.00 | ₹942.00 |
| 0018 | Hire and running charges of loader. | day | 0.12 | ₹6,700.00 | ₹804.00 |
| LABOUR | |||||
| 0128 | Mate | day | 0.04 | ₹816.00 | ₹32.64 |
| 0115 | Coolie | day | 0.06 | ₹736.00 | ₹44.16 |
| 9999 | Sundries (i.e. watch and ward, minor T&P etc.) | day | 3.1 | ₹2.27 | ₹7.04 |
Rate build-up
| TOTAL | ₹1,829.84 |
| Add 1 % Water charges on "W" | ₹18.30 |
| TOTAL | ₹1,848.14 |
| Add GST on "X" (multiplying factor 0.2127) | ₹393.10 |
| TOTAL | ₹2,241.24 |
| Add 15% CPOH on "Y" | ₹336.19 |
| TOTAL | ₹2,577.43 |
| Add Cess @ 1% on "Z" | ₹25.77 |
| Cost of 10 cum. | ₹2,603.20 |
| Cost of 1 cum. | ₹260.32 |
| Say | ₹260.30 |