DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.8.1 rate analysis

Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil.

Published rate₹260.30per cum
Rate analysis

Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.

DSR rate₹260.30per cum

All kinds of soil.

Item code
2.8.1
Sub-head
SH 2 · EARTH WORK
Unit
cum
Source row
213

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 cum.
MACHINERY
0020 Hydraulic Excavator (3D) with driver and fuel. day 0.12 ₹7,850.00 ₹942.00
0018 Hire and running charges of loader. day 0.12 ₹6,700.00 ₹804.00
LABOUR
0128 Mate day 0.04 ₹816.00 ₹32.64
0115 Coolie day 0.06 ₹736.00 ₹44.16
9999 Sundries (i.e. watch and ward, minor T&P etc.) day 3.1 ₹2.27 ₹7.04

Rate build-up

TOTAL ₹1,829.84
Add 1 % Water charges on "W" ₹18.30
TOTAL ₹1,848.14
Add GST on "X" (multiplying factor 0.2127) ₹393.10
TOTAL ₹2,241.24
Add 15% CPOH on "Y" ₹336.19
TOTAL ₹2,577.43
Add Cess @ 1% on "Z" ₹25.77
Cost of 10 cum. ₹2,603.20
Cost of 1 cum. ₹260.32
Say ₹260.30