DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.7.2 rate analysis

Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge. Hard rock (requiring blasting)

Published rate₹874.40per cum
Rate analysis

Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.

DSR rate₹874.40per cum

Hard rock (requiring blasting)

Item code
2.7.2
Sub-head
SH 2 · EARTH WORK
Unit
cum
Source row
134

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 cum.
MACHINERY
0020 Hydraulic Excavator (3D) with driver and fuel. day 0.125 ₹7,850.00 ₹981.25
0017 Hire and running charges of tipper day 0.125 ₹4,200.00 ₹525.00
LABOUR
0132 Rock Excavator day 1.06 ₹736.00 ₹780.16
0133 Rock Breaker day 2.825 ₹736.00 ₹2,079.20
0134 Rock Hole Driller day 0.885 ₹736.00 ₹651.36
0114 Beldar day 0.45 ₹736.00 ₹331.20
0115 Coolie day 0.55 ₹736.00 ₹404.80
0325 Blasting powder kilogram 3.93 ₹44.00 ₹172.92
0326 Blasting fuse (fuse wire) each 4 ₹46.00 ₹184.00
9999 Sundries L.S. 16.12 ₹2.27 ₹36.59

Rate build-up

TOTAL ₹6,146.48
Add 1 % Water charges on "W" ₹61.46
TOTAL ₹6,207.94
Add GST on "X" (multiplying factor 0.2127) ₹1,320.43
TOTAL ₹7,528.37
Add 15% CPOH on "Y" ₹1,129.26
TOTAL ₹8,657.63
Add Cess @ 1% on "Z" ₹86.58
Cost of 10 cum. ₹8,744.21
Cost of 1 cum. ₹874.42
Say ₹874.40

Use this rate in the interactive workbook