Rate analysis
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.
DSR rate₹874.40per cum
Hard rock (requiring blasting)
- Item code
- 2.7.2
- Sub-head
- SH 2 · EARTH WORK
- Unit
- cum
- Source row
- 134
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 cum. | |||||
| MACHINERY | |||||
| 0020 | Hydraulic Excavator (3D) with driver and fuel. | day | 0.125 | ₹7,850.00 | ₹981.25 |
| 0017 | Hire and running charges of tipper | day | 0.125 | ₹4,200.00 | ₹525.00 |
| LABOUR | |||||
| 0132 | Rock Excavator | day | 1.06 | ₹736.00 | ₹780.16 |
| 0133 | Rock Breaker | day | 2.825 | ₹736.00 | ₹2,079.20 |
| 0134 | Rock Hole Driller | day | 0.885 | ₹736.00 | ₹651.36 |
| 0114 | Beldar | day | 0.45 | ₹736.00 | ₹331.20 |
| 0115 | Coolie | day | 0.55 | ₹736.00 | ₹404.80 |
| 0325 | Blasting powder | kilogram | 3.93 | ₹44.00 | ₹172.92 |
| 0326 | Blasting fuse (fuse wire) | each | 4 | ₹46.00 | ₹184.00 |
| 9999 | Sundries | L.S. | 16.12 | ₹2.27 | ₹36.59 |
Rate build-up
| TOTAL | ₹6,146.48 |
| Add 1 % Water charges on "W" | ₹61.46 |
| TOTAL | ₹6,207.94 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,320.43 |
| TOTAL | ₹7,528.37 |
| Add 15% CPOH on "Y" | ₹1,129.26 |
| TOTAL | ₹8,657.63 |
| Add Cess @ 1% on "Z" | ₹86.58 |
| Cost of 10 cum. | ₹8,744.21 |
| Cost of 1 cum. | ₹874.42 |
| Say | ₹874.40 |