DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.22.1 rate analysis

Open timbering over areas including strutting, shoring etc. complete. (Measurements to be taken of the face area timbered): Depth not exceeding 1.5 m

Published rate₹44.85per sqm
Rate analysis

Open timbering over areas including strutting, shoring etc. complete. (Measurements to be taken of the face area timbered):

DSR rate₹44.85per sqm

Depth not exceeding 1.5 m

Item code
2.22.1
Sub-head
SH 2 · EARTH WORK
Unit
sqm
Source row
1472

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 area 30m long and 1.5m deep
area = 10x30 x 1.5 = 450 sqm.
MATERIAL
The Material can be used four times on the same work and after use of material credit is given @ 75% of cost
Polling boards of
1198 Second class kail wood in planks 10 cudm 35.625 ₹260.00 ₹9,262.50
250mm x 38mm
10x40x1.50x0.25x0.038 = 5.7cum. = 5700 dm³
Qty taken for cost of using once after
deducting for credit = 5700x¼x¼ = 356.25 dm³
Raking struts-
0302 Safeda ballies 125 mm diameter metre 37.5 ₹44.00 ₹1,650.00
10x40x1.50 = 600m
Qty taken for cost of using once after
deducting for credit = 600x¼x¼ = 37.5 m
2204 Carriage of Timber cum 3.275 ₹0.00 ₹0.00
CARRIAGE :
Poling boards = 5.7 cum
Ballies 10x40x1.5x3.14/4x0.125² = 7.4 cum.
Total for carriage = 13.1 cum x ¼ = 3.275 cum
LABOUR
0112 Carpenter 2nd class day 1.2 ₹816.00 ₹979.20
0114 Beldar day 2.5 ₹736.00 ₹1,840.00
9999 Sundries L.S. 197.6 ₹2.27 ₹448.55

Rate build-up

TOTAL ₹14,180.25
Add 1 % Water charges on "W" ₹141.80
TOTAL ₹14,322.05
Add GST on "X" (multiplying factor 0.2127) ₹3,046.30
TOTAL ₹17,368.35
Add 15% CPOH on "Y" ₹2,605.25
TOTAL ₹19,973.60
Add Cess @ 1% on "Z" ₹199.74
Cost of 450 sqm. ₹20,173.34
Cost per sqm. ₹44.83
Say ₹44.85