Rate analysis
Close timbering in trenches including strutting, shoring and packing cavities (wherever required) complete. (Measurements to be taken of the face area timbered).
DSR rate₹155.30per sqm
Depth exceeding 1.5 m but not exceeding 3 m
- Item code
- 2.16.2
- Sub-head
- SH 2 · EARTH WORK
- Unit
- sqm
- Source row
- 774
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 trench 30m long and 1.5m deep | |||||
| Area 10x2x30x1.50=900 sqm | |||||
| MATERIAL | |||||
| The Material can be used four times on the same work and after use of material credit is given @ 75% of cost | |||||
| Poling boards of | |||||
| 1198 | Second class kail wood in planks | 10 cudm | 213.75 | ₹260.00 | ₹55,575.00 |
| 900x0.038 = 34.2 cum = 34200 cudm | |||||
| Qty taken for cost of using once | |||||
| after deducting for credit = 34200x¼x¼ = 2137.5 dm³ | |||||
| Walings 100 mmx 100mm of | |||||
| 1197 | Second class kail wood in scantling | 10 cudm | 75 | ₹260.00 | ₹19,500.00 |
| 10x4x30x0.10x0.10 = 12cum = 12000 cudm | |||||
| Qty taken for cost of using once after deducting for credit = 12000x¼x¼ = 750 dm³ | |||||
| 0302 | Safeda ballies 125 mm diameter | metre | 31.875 | ₹44.00 | ₹1,402.50 |
| and 1.5m long | |||||
| 10x2x17x1.50 = 510m | |||||
| Qty taken for cost of using once | |||||
| after deducting for credit = 510x¼x¼ = 31.875 m | |||||
| CARRIAGE | |||||
| 2204 | Carriage of Timber | cum | 13.125 | ₹0.00 | ₹0.00 |
| Poling boards = 34.2 cum | |||||
| Walling= 12 cum. | |||||
| Balli struts: 3.14/4x(0.125)³x510 = 6.3 cum | |||||
| Total of carriage = 52.5x¼ = 13.125 cum. | |||||
| 0112 | Carpenter 2nd class | day | 7.5 | ₹816.00 | ₹6,120.00 |
| 0114 | Beldar | day | 20 | ₹736.00 | ₹14,720.00 |
| 9999 | Sundries | L.S. | 404.3 | ₹2.27 | ₹917.76 |
Rate build-up
| TOTAL | ₹98,235.26 |
| Add 1 % Water charges on "W" | ₹982.35 |
| TOTAL | ₹99,217.61 |
| Add GST on "X" (multiplying factor 0.2127) | ₹21,103.59 |
| TOTAL | ₹1,20,321.20 |
| Add 15% CPOH on "Y" | ₹18,048.18 |
| TOTAL | ₹1,38,369.38 |
| Add Cess @ 1% on "Z" | ₹1,383.69 |
| Cost of 900 Sqm. | ₹1,39,753.07 |
| Cost per sqm. | ₹155.28 |
| Say | ₹155.30 |