DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.1.1 rate analysis

Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m, as directed by Engineer-in- Charge: All kinds of soil

Published rate₹129.85per sqm
Rate analysis

Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m, as directed by Engineer-in- Charge:

DSR rate₹129.85per sqm

All kinds of soil

Item code
2.1.1
Sub-head
SH 2 · EARTH WORK
Unit
sqm
Source row
4

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 100 Sqm
LABOUR
0114 Beldar day 6.8 ₹736.00 ₹5,004.80
0115 Coolie day 5.6 ₹736.00 ₹4,121.60

Rate build-up

TOTAL ₹9,126.40
Add 1 % Water charges on "W" ₹91.26
TOTAL ₹9,217.66
Add GST on "X" (multiplying factor 0.2127) ₹1,960.60
TOTAL ₹11,178.26
Add 15% CPOH on "Y" ₹1,676.74
TOTAL ₹12,855.00
Add Cess @ 1% on "Z" ₹128.55
Cost of 100 sqm ₹12,983.55
Cost of 1 sqm ₹129.84
Say ₹129.85