Rate analysis
Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m, as directed by Engineer-in- Charge:
DSR rate₹129.85per sqm
All kinds of soil
- Item code
- 2.1.1
- Sub-head
- SH 2 · EARTH WORK
- Unit
- sqm
- Source row
- 4
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 100 Sqm | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 6.8 | ₹736.00 | ₹5,004.80 |
| 0115 | Coolie | day | 5.6 | ₹736.00 | ₹4,121.60 |
Rate build-up
| TOTAL | ₹9,126.40 |
| Add 1 % Water charges on "W" | ₹91.26 |
| TOTAL | ₹9,217.66 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,960.60 |
| TOTAL | ₹11,178.26 |
| Add 15% CPOH on "Y" | ₹1,676.74 |
| TOTAL | ₹12,855.00 |
| Add Cess @ 1% on "Z" | ₹128.55 |
| Cost of 100 sqm | ₹12,983.55 |
| Cost of 1 sqm | ₹129.84 |
| Say | ₹129.85 |