DSR 2023 · SH 19 · DRAINAGE

CPWD DSR item 19.24.1 rate analysis

Dismantling of manhole including R.C.C. top slab, C.I. cover with frame, including stacking of useful materials near the site and disposal of unserviceable materials within 50 m lead as per direction of Engineer-in-charge: Rectangular manhole 90x80 cm and 45 cm deep

Published rate₹2,540.85DSR 2023
Rate analysis

Dismantling of manhole including R.C.C. top slab, C.I. cover with frame, including stacking of useful materials near the site and disposal of unserviceable materials within 50 m lead as per direction of Engineer-in-charge:

DSR rate₹2,540.85as per item analysis

Rectangular manhole 90x80 cm and 45 cm deep

Item code
19.24.1
Sub-head
SH 19 · DRAINAGE
Unit
See analysis
Source row
2696

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost of a manhole 90x80 cm and 45 cm deep
Dismantling of cement concrete 1:4:8 (1 cement : 4 coarse sand 8 : aggregate stone 40 mm nominal size)
1.51x1.41x0.20 m = 0.426 cum Say 0.43 cum
15.2.2 Rate as per item no. 15.2.2 of SH : Dismantling and demolishing cum 0.43 ₹1,503.60 ₹646.55
Dismantling of secon class brick work in cement mortar 1:4 (1 cement : 4 coarse sand)
4.32x0.23x0.35 m = 0.348 cum
Less for pipe 2x3.14x(0.15m)² x0.23m = (-) 0.008 cum
Net Qty 0.348 - 0.008 = 0.340 cum
15.7.4 Rate as per item no. 15.7.4 of SH :dismantling and dimolishing cum 0.34 ₹2,060.20 ₹700.47
Dismantling cement concrete 1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
For benching 2x0.90x(0.80/2) x(0.30+0.20)/2 = 0.18 cum
Less for pipe 1x0.90x3.14/4x(0.15m)² = (-) 0.02 cum
Net qty= 0.16 cum
15.2.1 Rate as per item no. 15.2.1 of SH : Dismantling and demolishing cum 0.16 ₹2,434.25 ₹389.48
Dismantling of R.C.C slab of 1:2:4 (1 cement : 2 coarse sand : 4 grade stone aggregate 20 mm nominal size)
For slab : 1.36x1.26x0.15m = 0.257 cum
Less for cover 0.61x0.455x0.15m = (-) 0.042 cum
Net qty= 0.215 cum Say 0.22 cum
15.3 Rate as per item no 15.3 of SH : Demolishing and dismantling cum 0.22 ₹3,551.25 ₹781.28
9999 Removal of C.I. Cover with frame L.S. 7.15 ₹2.27 ₹16.23

Rate build-up

TOTAL ₹2,534.01
Add 1 % Water charges on "W-A" ₹0.16
TOTAL ₹2,534.17
Add GST on "X-A" (multiplying factor 0.2127) ₹3.49
TOTAL ₹2,537.66
Add 15% CPOH on "Y-A" ₹2.98
TOTAL ₹2,540.64
Add Cess @ 1% on "Z-A" ₹0.23
Cost of one no ₹2,540.87
Say ₹2,540.85