CPWD DSR item 19.24.2 rate analysis

Dismantling of manhole including R.C.C. top slab, C.I. cover with frame, including stacking of useful materials near the site and disposal of unserviceable materials within 50 m lead as per direction of Engineer-in-charge: Rectangular manhole 120x90 cm and 90 cm deep

Published rate₹4,475.50DSR 2023
Rate analysis

Dismantling of manhole including R.C.C. top slab, C.I. cover with frame, including stacking of useful materials near the site and disposal of unserviceable materials within 50 m lead as per direction of Engineer-in-charge:

DSR rate₹4,475.50as per item analysis

Rectangular manhole 120x90 cm and 90 cm deep

Item code
19.24.2
Sub-head
SH 19 · DRAINAGE
Unit
See analysis
Source row
2696

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost of a manhole 120x90 and 90 cm deep
Dismantling of cement concrete 1:4:8 (1 cement : 4 coarse sand 8 : aggregate stone 40 mm nominal size)
1.81x1.51x0.20 m = 0.547 cum Say 0.55 cum
15.2.2 Rate as per item no. 15.2.2 of SH : Dismantling and demolishing cum 0.55 ₹1,503.60 ₹826.98
Dismantling of secon class brick work in cement mortar 1:4 (1 cement : 4 coarse sand)
5.12x0.23x0.80 m = 0.942 cum
Less for pipe 2x3.14x(0.15m)²x0.23 m = (-) 0.008 cum
Net qty = 0.934 cum Say 0.93 cum
15.7.4 Rate as per item no. 15.7.4 of SH :dismantling and dimolishing cum 0.93 ₹2,060.20 ₹1,915.99
Dismantling cement concrete 1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
2x1.20x0.90x(0.80/2) x (0.30+0.20)/2 = 2.70 cum
Less for pipe 1.20x3.14/4x(0.15m)² = (-) 0.021 cum
= 0.249 cum say 0.25
15.2.1 Rate as per item no. 15.2.1 of SH : Dismantling and demolishing cum 0.25 ₹2,434.25 ₹608.56
Dismantling of R.C.C slab of 1:2:4 (1 cement : 2 coarse sand : 4 grade stone aggregate 20 mm nominal size)
For slab : 1.66x1.36x0.15m = 0.339 cum
Less for cover 3.14/4x(0.50)²x0.15m = (-) 0.029 cum
Net qty = 0.31 cum
15.3 Rate as per item no 15.3 of SH : Demolishing and dismantling cum 0.31 ₹3,551.25 ₹1,100.89
9999 Removal of C.I. Cover with frame L.S. 7.15 ₹2.27 ₹16.23

Rate build-up

TOTAL ₹4,468.65
Add 1 % Water charges on "W-A" ₹0.16
TOTAL ₹4,468.81
Add GST on "X-A" (multiplying factor 0.2127) ₹3.49
TOTAL ₹4,472.30
Add 15% CPOH on "Y-A" ₹2.98
TOTAL ₹4,475.28
Add Cess @ 1% on "Z-A" ₹0.23
Cost of one no ₹4,475.51
Say ₹4,475.50