Rate analysis
Extra for depths beyond 60 cm of sand cast iron drop connection complete:
DSR rate₹4,126.90as per item analysis
For 150 mm dia sand cast iron drop connection
- Item code
- 19.23.2
- Sub-head
- SH 19 · DRAINAGE
- Unit
- See analysis
- Source row
- 2621
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for one metre | |||||
| MATERIAL | |||||
| 1618 | S.C.I. soil, waste and vent single socketed pipe 1.80 metres long: 150mm dia | each | 0.556 | ₹1,800.00 | ₹1,000.80 |
| Length of pipe = 1m. Hence, Qty | |||||
| = 1 / 1.8 = 0.556 Nos. | |||||
| 9977 | Carriage of material and fixing charges | L.S. | 13.39 | ₹2.27 | ₹30.40 |
| Cement concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size) | |||||
| 0.45x0.50x1.00 mm = 0.225 cum | |||||
| Less pipe portion | |||||
| 1/2x3.14x0.15x0.15x1.00 = 0.018 cum | |||||
| Toothing portion | |||||
| 5x0.45x0.05x0.10 m = 0.011 cum | |||||
| Total = 0.029 cum | |||||
| Net 0.225-0.029 = 0.196 cum Say 0.20 cum | |||||
| 4.1.11 | Rate as per item no 4.1.11 of SH : Concrete Work | cum | 0.2 | ₹6,189.65 | ₹1,237.93 |
| Form work | |||||
| 1.45x1.00 m = 1.45 sqm | |||||
| 5.9.2 | Rate as per item no 5.9.2 of SH : RCC | sqm | 1.45 | ₹842.50 | ₹1,221.63 |
| 9999 | Sundries | L.S. | 8.09 | ₹2.27 | ₹18.36 |
| LABOUR | |||||
| For cutting 5 cm deep in alternate course of brick work | |||||
| 0123 | Mason 1st class | day | 0.05 | ₹897.00 | ₹44.85 |
| 0124 | Mason 2nd class | day | 0.05 | ₹816.00 | ₹40.80 |
| 0114 | Beldar | day | 0.05 | ₹736.00 | ₹36.80 |
Rate build-up
| TOTAL | ₹3,631.57 |
| Add 1 % Water charges on "W-A" | ₹11.72 |
| TOTAL | ₹3,643.29 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹251.78 |
| TOTAL | ₹3,895.07 |
| Add 15% CPOH on "Y-A" | ₹215.33 |
| TOTAL | ₹4,110.40 |
| Add Cess @ 1% on "Z-A" | ₹16.51 |
| Cost of one metre | ₹4,126.91 |
| Say | ₹4,126.90 |