DSR 2023 · SH 18 · WATER SUPPLY

CPWD DSR item 18.77 rate analysis

Cutting holes up to 15x15 cm in R.C.C. floors and roofs for passing drain pipe etc. and repairing the hole after insertion of drain pipe etc. with cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size), including finishing complete so as to make it leak proof.

Published rate₹452.00per hole
Rate analysis

Cutting holes up to 15x15 cm in R.C.C. floors and roofs for passing drain pipe etc. and repairing the hole after insertion of drain pipe etc. with cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size), including finishing complete so as to make it leak proof.

DSR rate₹452.00per hole
Item code
18.77
Sub-head
SH 18 · WATER SUPPLY
Unit
hole
Source row
8075

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 holes
Average size 15x15x15 cm
Labour for cutting holes
0123 Mason 1st class day 0.83 ₹897.00 ₹744.51
0124 Mason 2nd class day 0.83 ₹816.00 ₹677.28
0114 Beldar day 1.67 ₹736.00 ₹1,229.12
Cement concrete 1:2:4 (1 cement : 2 coarse sand ; 4 graded stone aggregate 20 mm nominal size)
10x0.15x0.15x0.15 m = 0.033 cum
Les 33% for pipe etc. = (-) 0.011 cum
= 0.022 cum Say 0.0.02 cum
4.1.3 Rate as per item no. 4.1.3 of SH : concrete Work cum 0.02 ₹7,878.50 ₹157.57
9999 Finishing top and bottom and making the holes leak proof L.S. 121.16 ₹2.27 ₹275.03
9999 Add for delay L.S. 40.3 ₹2.27 ₹91.48
9999 Sundries L.S. 21.58 ₹2.27 ₹48.99

Rate build-up

TOTAL ₹3,223.98
Add 1 % Water charges on "W-A" ₹30.66
TOTAL ₹3,254.64
Add GST on "X-A" (multiplying factor 0.2127) ₹658.75
TOTAL ₹3,913.39
Add 15% CPOH on "Y-A" ₹563.37
TOTAL ₹4,476.76
Add Cess @ 1% on "Z-A" ₹43.19
Cost of 10 holes ₹4,519.95
Cost of 1 hole ₹452.00
Say ₹452.00

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook