DSR 2023 · SH 18 · WATER SUPPLY

CPWD DSR item 18.78 rate analysis

Making chases up to 7.5x7.5 cm in walls including making good and finishing with matching surface after housing G.I. pipe etc.

Published rate₹202.90per metre
Rate analysis

Making chases up to 7.5x7.5 cm in walls including making good and finishing with matching surface after housing G.I. pipe etc.

DSR rate₹202.90per metre
Item code
18.78
Sub-head
SH 18 · WATER SUPPLY
Unit
metre
Source row
8103

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 metres
Labour for making chases
0123 Mason 1st class day 0.25 ₹897.00 ₹224.25
0124 Mason 2nd class day 0.25 ₹816.00 ₹204.00
0114 Beldar day 1 ₹736.00 ₹736.00
Cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
0.075x0.075x10 m = 0.05625 cum
Les 33% for pipe etc. = (-) 0.01856 cum
= 0.03769 cum Say 0.04 cum
4.2.5 Rate as per item no 4.2.5 of SH : Concrete work cum 0.04 ₹9,311.40 ₹372.46

Rate build-up

TOTAL ₹1,536.71
Add 1 % Water charges on "W-A" ₹11.64
TOTAL ₹1,548.35
Add GST on "X-A" (multiplying factor 0.2127) ₹250.11
TOTAL ₹1,798.46
Add 15% CPOH on "Y-A" ₹213.90
TOTAL ₹2,012.36
Add Cess @ 1% on "Z-A" ₹16.40
Cost of 10 metre ₹2,028.76
Cost of 1 metre ₹202.88
Say ₹202.90