DSR 2023 · SH 18 · WATER SUPPLY

CPWD DSR item 18.76.1 rate analysis

Cutting holes up to 30x30 cm in walls including making good the same: With common burnt clay F.P.S. (non modular) bricks

Published rate₹416.80per hole
Rate analysis

Cutting holes up to 30x30 cm in walls including making good the same:

DSR rate₹416.80per hole

With common burnt clay F.P.S. (non modular) bricks

Item code
18.76.1
Sub-head
SH 18 · WATER SUPPLY
Unit
hole
Source row
8042

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 holes
Size 30x30 cm in 34 cm wall
Labour for cutting holes
0123 Mason 1st class day 0.16 ₹897.00 ₹143.52
0124 Mason 2nd class day 0.16 ₹816.00 ₹130.56
0114 Beldar day 1.25 ₹736.00 ₹920.00
Brick work with bricks of class designation 75 in cement mortar 1:4 (1 cement : 4 coarse sand)
10x0.30x0.30x0.344m = 0.309 cum
Less 33% for pipe etc. = (-) 0.102 cum
= 0.207 cum Say 0.21 cum
6.4.1 Rate as per item No 6.4.1 of SH :- Brick work. cum 0.21 ₹9,344.35 ₹1,962.31
12 mm cement plaster 1:4 (1 cement : 4 coarse sand)
10x2x0.3x0.3m = 1.80 sqm
Les 33% for pipe etc. = (-) 0.59 sqm
= 1.21 sqm Say 1.20 sqm
13.4.1 (Rate as per item no 13.4.1 of SH : Finishing) sqm 1.2 ₹357.35 ₹428.82
9999 Add for delay L.S. 16.12 ₹2.27 ₹36.59
9999 Sundries L.S. 8.06 ₹2.27 ₹18.30

Rate build-up

TOTAL ₹3,640.10
Add 1 % Water charges on "W-A" ₹12.49
TOTAL ₹3,652.59
Add GST on "X-A" (multiplying factor 0.2127) ₹268.31
TOTAL ₹3,920.90
Add 15% CPOH on "Y-A" ₹229.47
TOTAL ₹4,150.37
Add Cess @ 1% on "Z-A" ₹17.59
Cost of 10 holes ₹4,167.96
Cost of 1 hole ₹416.80
Say ₹416.80

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook