Variant 1
Scarifying metalled (water-bound) road surface including disposal of rubbish, lead upto 50 m and consolidation of the aggregate received from scarifying with power road roller of 8 to 10 tonne capacity.
DSR rate₹33.30per sqm
- Item code
- 16.9
- Sub-head
- SH 16 · ROAD WORK
- Unit
- sqm
- Source row
- 388
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 100sqm. | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 1.35 | ₹736.00 | ₹993.60 |
| 0115 | Coolie | day | 1.08 | ₹736.00 | ₹794.88 |
| Consolidation of scarified material | |||||
| 100sqm.x50mm = 5cum + | |||||
| Less 20% wastage = 1 cum. | |||||
| = 4 cum. | |||||
| 0003 | Hire charges of Diesel Road Roller - 8 to 10 tonne | day | 0.132 | ₹3,350.00 | ₹442.20 |
| 0113 | Chowkidar | day | 0.132 | ₹736.00 | ₹97.15 |
| 9999 | Sundries | L.S. | 5.46 | ₹2.27 | ₹12.39 |
Rate build-up
| TOTAL | ₹2,340.22 |
| Add 1 % Water charges on "W" | ₹23.40 |
| TOTAL | ₹2,363.62 |
| Add GST on "X" (multiplying factor 0.2127) | ₹502.74 |
| TOTAL | ₹2,866.36 |
| Add 15% CPOH on "Y" | ₹429.95 |
| TOTAL | ₹3,296.31 |
| Add Cess @ 1% on "Z" | ₹32.96 |
| Cost for 100 sqm. | ₹3,329.27 |
| Cost per sqm. | ₹33.29 |
| Say | ₹33.30 |