Rate analysis
Brick edging laid lengthwise with half brick depth including excavation, refilling and disposal of surplus earth lead upto 50 metres :
DSR rate₹53.45per metre
With common burnt clay F.P.S. (non modular) bricks of class designation 7.5
- Item code
- 16.8.1
- Sub-head
- SH 16 · ROAD WORK
- Unit
- metre
- Source row
- 363
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 metre | |||||
| MATERIAL | |||||
| 2602 | Common burnt clay F.P.S. (non modular) bricks class designation 7.5 | 1000 Nos | 0.049 | ₹4,724.00 | ₹231.48 |
| including 12% wastage | |||||
| 2201 | Carriage of Bricks | 1000 Nos | 0.049 | ₹0.00 | ₹0.00 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 0.04 | ₹897.00 | ₹35.88 |
| 0124 | Mason 2nd class | day | 0.04 | ₹816.00 | ₹32.64 |
| 0115 | Coolie | day | 0.09 | ₹736.00 | ₹66.24 |
| 9999 | Removal of rubbish | L.S. | 4.16 | ₹2.27 | ₹9.44 |
Rate build-up
| TOTAL | ₹375.68 |
| Add 1 % Water charges on "W" | ₹3.76 |
| TOTAL | ₹379.44 |
| Add GST on "X" (multiplying factor 0.2127) | ₹80.71 |
| TOTAL | ₹460.15 |
| Add 15% CPOH on "Y" | ₹69.02 |
| TOTAL | ₹529.17 |
| Add Cess @ 1% on "Z" | ₹5.29 |
| Cost for 10 metre | ₹534.46 |
| Cost per metre | ₹53.45 |
| Say | ₹53.45 |