DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.82 rate analysis

Taking out existing kerb stones of all types from footpath/ central verge, including removal of mortar etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge.

Published rate₹39.35per metre
Rate analysis

Taking out existing kerb stones of all types from footpath/ central verge, including removal of mortar etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge.

DSR rate₹39.35per metre
Item code
16.82
Sub-head
SH 16 · ROAD WORK
Unit
metre
Source row
5107

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 100 metre
LABOUR
0114 Beldar day 0.75 ₹736.00 ₹552.00
0115 Coolie day 3 ₹736.00 ₹2,208.00
9999 Sundries L.S. 2 ₹2.27 ₹4.54

Rate build-up

TOTAL ₹2,764.54
Add 1 % Water charges on "W" ₹27.65
TOTAL ₹2,792.19
Add GST on "X" (multiplying factor 0.2127) ₹593.90
TOTAL ₹3,386.09
Add 15% CPOH on "Y" ₹507.91
TOTAL ₹3,894.00
Add Cess @ 1% on "Z" ₹38.94
Cost of 100 metre ₹3,932.94
Cost of 1 metre ₹39.33
Say ₹39.35

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook