Rate analysis
Taking out existing kerb stones of all types from footpath/ central verge, including removal of mortar etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge.
DSR rate₹39.35per metre
- Item code
- 16.82
- Sub-head
- SH 16 · ROAD WORK
- Unit
- metre
- Source row
- 5107
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 100 metre | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 0.75 | ₹736.00 | ₹552.00 |
| 0115 | Coolie | day | 3 | ₹736.00 | ₹2,208.00 |
| 9999 | Sundries | L.S. | 2 | ₹2.27 | ₹4.54 |
Rate build-up
| TOTAL | ₹2,764.54 |
| Add 1 % Water charges on "W" | ₹27.65 |
| TOTAL | ₹2,792.19 |
| Add GST on "X" (multiplying factor 0.2127) | ₹593.90 |
| TOTAL | ₹3,386.09 |
| Add 15% CPOH on "Y" | ₹507.91 |
| TOTAL | ₹3,894.00 |
| Add Cess @ 1% on "Z" | ₹38.94 |
| Cost of 100 metre | ₹3,932.94 |
| Cost of 1 metre | ₹39.33 |
| Say | ₹39.35 |