Rate analysis
Taking out existing CC interlocking paver blocks from footpath/ central verge, including removal of rubbish etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge.
DSR rate₹131.75per sqm
- Item code
- 16.83
- Sub-head
- SH 16 · ROAD WORK
- Unit
- sqm
- Source row
- 5127
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 sqm. | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 0.25 | ₹736.00 | ₹184.00 |
| 0115 | Coolie | day | 1 | ₹736.00 | ₹736.00 |
| 9999 | Sundries | L.S. | 2.7 | ₹2.27 | ₹6.13 |
Rate build-up
| TOTAL | ₹926.13 |
| Add 1 % Water charges on "W" | ₹9.26 |
| TOTAL | ₹935.39 |
| Add GST on "X" (multiplying factor 0.2127) | ₹198.96 |
| TOTAL | ₹1,134.35 |
| Add 15% CPOH on "Y" | ₹170.15 |
| TOTAL | ₹1,304.50 |
| Add Cess @ 1% on "Z" | ₹13.05 |
| Cost of 10 sqm. | ₹1,317.55 |
| Cost of 1 sqm | ₹131.76 |
| Say | ₹131.75 |