DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.81Y rate analysis

Sub analysis item for fabrication charges of Item No. 16.81

Published rate₹1,673.35per metre
Rate analysis

Sub analysis item for fabrication charges of Item No. 16.81

DSR rate₹1,673.35per metre
Item code
16.81Y
Sub-head
SH 16 · ROAD WORK
Unit
metre
Source row
5081

Cost components

CodeDescriptionUnitQuantityRateAmount
Sub analysis item no.16.81Y to be used in Item No. 16.81
Details of cost for 2.5 metre
MATERIAL
1215 Welding by electric plant cm 165 ₹2.50 ₹412.50
Cutting, assembling and erection charges
LABOUR
0102 Blacksmith 1st class day 0.115 ₹897.00 ₹103.16
0103 Blacksmith 2nd class day 0.115 ₹816.00 ₹93.84
0100 Bandhani day 0.11 ₹816.00 ₹89.76
0114 Beldar day 0.83 ₹736.00 ₹610.88
9999 Sundries L.S. 12.1 ₹2.27 ₹27.47
Labour for riveting / bolting / cutting etc.
0116 Fitter (grade 1) day 0.41 ₹897.00 ₹367.77
0103 Blacksmith 2nd class day 0.54 ₹816.00 ₹440.64
0100 Bandhani day 0.7 ₹816.00 ₹571.20
0114 Beldar day 0.54 ₹736.00 ₹397.44
0139 Skilled Beldar (for floor rubbing etc.) day 0.81 ₹816.00 ₹660.96
9999 Sundries L.S. 12.1 ₹2.27 ₹27.47
Shifting including transportation, re-erection etc. @ 10% ₹380.31
TOTAL Cost of 2.5 metre ₹4,183.40

Rate build-up

TOTAL ₹3,803.09
Cost of 1 metre ₹1,673.36
Say ₹1,673.35