DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.81X rate analysis

Sub analysis item for material component of Item No. 16.81

Published rate₹53.70per metre
Rate analysis

Sub analysis item for material component of Item No. 16.81

DSR rate₹53.70per metre
Item code
16.81X
Sub-head
SH 16 · ROAD WORK
Unit
metre
Source row
5039

Cost components

CodeDescriptionUnitQuantityRateAmount
Sub analysis item no.16.81X to be used in Item No. 16.81
Details of cost for 2.5 metre
MATERIAL
M.S. Sheet 1.63mm thick = 1x2.50x2.00
= 5.00 sqm @ 12.80 kg/sqm = 64.00 kg
wastage @ 5%= 3.20 kg
Total = 67.20 kg
1013 Mild steel sheets for tanks quintal 0.672 ₹5,500.00 ₹3,696.00
MS Angle - 40 x 40 x 6 mm
Outframe=2x(2.50+2.00)=9.00 m
Vertical extra = 2x0.300 = 0.60 m
Horizontal = 1x2.50 =2.50 m
Bracing = 2x3.20 = 6.40 m
Bracing at bottom = 2x0.50 = 1.00 m
Total = 19.50 m @ 3.50 kg/m = 68.25 kg +
wastage @ 5% = 3.14 kg
Total = 71.66 kg
1007 Structurals such as tees,angles channels and R.S. joists quintal 0.717 ₹5,965.00 ₹4,276.91
M.S. Channel = 2x0.50 =1.00 m @
5.70 kg/m = 5.70 kg+
wastage @ 5% = 0.29 kg
Total = 5.99 kg
1007 Structurals such as tees, angles channels and R.S. joists quintal 0.0599 ₹5,965.00 ₹357.30
M.S. Flat 30x5 mm
Horizontal = 2x2.50 = 5.00 m
Vertical = 2x2.00 = 4.00 m
Total = 9.00 m @ 1.20 kg/m = 10.80 kg +
wastage @ 5% = 0.54 kg
Total = 11.34 kg
1008 Flats upto 10 mm in thickness quintal 0.1134 ₹5,450.00 ₹618.03
2205 Carriage of Steel tonne 0.156 ₹0.00 ₹0.00
Add for maintenance @ 10% on P ₹894.82
Less for salvage value of material @ 50% on P -₹4,474.12
Assuming that material will become unserviceable after using 40 times, cost of 2.5 metre using once = S/40

Rate build-up

TOTAL ₹8,948.24
TOTAL ₹5,368.94
Cost of 2.5 metre ₹134.22
Cost of 1 metre ₹53.69
Say ₹53.70