Rate analysis
Deduct for using of M-20 grade concrete instead of M-25 grade concrete in C.C. pavement.
DSR rate₹203.80as per item analysis
- Item code
- 16.76
- Sub-head
- SH 16 · ROAD WORK
- Unit
- See analysis
- Source row
- 4736
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| Cement for M-25 mix = 0.410 t | |||||
| Cement for M - 20 mix = 0.383 t | |||||
| Difference = 0.027 t | |||||
| METERIAL | |||||
| 0367 | Portland Cement (OPC-43 grade) | tonne | 0.027 | ₹5,156.00 | ₹139.21 |
| 2209 | Carriage of Cement | tonne | 0.027 | ₹0.00 | ₹0.00 |
| Plasticizer for M- 25 mix = 2.050kg | |||||
| Plasticizer for M- 20 mix = 1.915 kg | |||||
| Difference = 0.135 kg | |||||
| 7318 | Plasticizer / super plasticizer | kilogram | 0.135 | ₹30.00 | ₹4.05 |
Rate build-up
| TOTAL | ₹143.26 |
| Add 1 % Water charges on "W" | ₹1.43 |
| TOTAL | ₹144.69 |
| Add GST on "X" (multiplying factor 0.2127) | ₹30.78 |
| TOTAL | ₹175.47 |
| Add 15% CPOH on "Y" | ₹26.32 |
| TOTAL | ₹201.79 |
| Add Cess @ 1% on "Z" | ₹2.02 |
| Cost for 1 cum. | ₹203.81 |
| Say | ₹203.80 |