DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.75 rate analysis

Providing and laying C.C. pavement of mix M-25 with ready mixed concrete from batching plant. The ready mixed concrete shall be laid and finished with screed board vibrator , vacuum dewatering process and finally finished by floating, brooming with wire brush etc. complete as per specifications and directions of Engineer-in-charge. (The panel shuttering work shall be paid for separately). (Note:- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used as per design mix is payable/ recoverable separately).

Published rate₹9,823.80DSR 2023
Rate analysis

Providing and laying C.C. pavement of mix M-25 with ready mixed concrete from batching plant. The ready mixed concrete shall be laid and finished with screed board vibrator , vacuum dewatering process and finally finished by floating, brooming with wire brush etc. complete as per specifications and directions of Engineer-in-charge. (The panel shuttering work shall be paid for separately). (Note:- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used as per design mix is payable/ recoverable separately).

DSR rate₹9,823.80as per item analysis
Item code
16.75
Sub-head
SH 16 · ROAD WORK
Unit
See analysis
Source row
4715

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1.00 cum
MATERIAL
Ready mix concrete M 25 = 1.00 cum. i/c placing of concrete, vibrating, leveling etc
5.33.1.1 Rate as per Item No.5.33.1.1 of SH:RCC cum 1 ₹9,504.75 ₹9,504.75
9999 Operational charges for vacuum dewatering system i/c screed vibration, placing of filter mat , top mat, vacuum process, floating , troweling, Brooming etc L.S. 57.2 ₹2.27 ₹129.84
9999 T& P charges i/c consumable power charges, loading , unloading and hire charges of equipments L.S. 41.6 ₹2.27 ₹94.43

Rate build-up

TOTAL ₹9,729.02
Add 1 % Water charges on "W-A" ₹2.24
TOTAL ₹9,731.26
Add GST on "X-A" (multiplying factor 0.2127) ₹48.18
TOTAL ₹9,779.44
Add 15% CPOH on "Y-A" ₹41.20
TOTAL ₹9,820.64
Add Cess @ 1% on "Z-A" ₹3.16
Cost for 1 cum ₹9,823.80
Cost for 1 cum ₹9,823.80
Say ₹9,823.80