Rate analysis
Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material within all lifts and lead upto 1km (by mechanical means).
DSR rate₹7.00as per item analysis
- Item code
- 16.77
- Sub-head
- SH 16 · ROAD WORK
- Unit
- See analysis
- Source row
- 4760
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 100 sqm | |||||
| LABOUR | |||||
| 0128 | Mate | day | 0.01 | ₹816.00 | ₹8.16 |
| 0114 | Beldar | day | 0.25 | ₹736.00 | ₹184.00 |
| MACHINERY | |||||
| 0038 | Tractor with ripper attachment. | day | 0.01 | ₹1,350.00 | ₹13.50 |
| 0014 | Front end loader capacity 1.00 cum | day | 0.025 | ₹6,700.00 | ₹167.50 |
| 0017 | Hire and running charges of tipper | day | 0.028 | ₹4,200.00 | ₹117.60 |
Rate build-up
| TOTAL | ₹490.76 |
| Add 1 % Water charges on "W" | ₹4.91 |
| TOTAL | ₹495.67 |
| Add GST on "X" (multiplying factor 0.2127) | ₹105.43 |
| TOTAL | ₹601.10 |
| Add 15% CPOH on "Y" | ₹90.17 |
| TOTAL | ₹691.27 |
| Add Cess @ 1% on "Z" | ₹6.91 |
| Cost for 100 sqm | ₹698.18 |
| Cost for 1 sqm | ₹6.98 |
| Say | ₹7.00 |