DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.36.1 rate analysis

Providing and laying Bitumen Penetration Macadam with hard stone aggregate of quality, size and grading as specified, with bitumen of suitable penetration grade, including required key aggregate as specified, spreading coarse aggregate with the help of self propelled/ tipper tail mounted aggregate spreader and applying bitumen by a pressure distributor and then spreading key aggregate with the help of aggregate spreader complete, including consolidation with road roller of minimum 8 to 10 tonne capacity to achieve specified values of compaction and surface accuracy : For 50mm compacted thickness using coarse aggregate of size 50-20 mm graded @ 0.60 cum per 10 sqm key aggregate of size 12.5 mm graded @ 0.15 cum per 10 sqm. With paving asphalt grade VG - 10 @ 50 kg/ 10 sqm.

Published rate₹505.65per sqm
Rate analysis

Providing and laying Bitumen Penetration Macadam with hard stone aggregate of quality, size and grading as specified, with bitumen of suitable penetration grade, including required key aggregate as specified, spreading coarse aggregate with the help of self propelled/ tipper tail mounted aggregate spreader and applying bitumen by a pressure distributor and then spreading key aggregate with the help of aggregate spreader complete, including consolidation with road roller of minimum 8 to 10 tonne capacity to achieve specified values of compaction and surface accuracy :

DSR rate₹505.65per sqm

For 50mm compacted thickness using coarse aggregate of size 50-20 mm graded @ 0.60 cum per 10 sqm key aggregate of size 12.5 mm graded @ 0.15 cum per 10 sqm. With paving asphalt grade VG - 10 @ 50 kg/ 10 sqm.

Item code
16.36.1
Sub-head
SH 16 · ROAD WORK
Unit
sqm
Source row
1980

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 370 sqm.
MATERIAL
Taking stone aggregate 40mm = 45%
20mm = 44%
11.2mm = 8%
Stone dust = 3%
0293 Stone Aggregate (Single size) : 40 mm nominal size cum 9.99 ₹1,400.00 ₹13,986.00
0295 Stone Aggregate (Single size) : 20 mm nominal size cum 9.77 ₹1,425.00 ₹13,922.25
0297 Stone Aggregate (Single size) : 10 mm nominal size cum 1.78 ₹1,400.00 ₹2,492.00
1159 Stone dust cum 0.6 ₹1,100.00 ₹660.00
0295 Stone Aggregate (Single size) : 20 mm nominal size cum 2.33 ₹1,425.00 ₹3,320.25
0296 Stone Aggregate (Single size) : 12.5 mm nominal size cum 2.66 ₹1,400.00 ₹3,724.00
1159 Stone dust cum 0.56 ₹1,100.00 ₹616.00
2206 Carriage of Stone aggregate 40 mm nominal size and above cum 9.99 ₹0.00 ₹0.00
2202 Carriage of Stone aggregate below 40 mm nominal size i.e. 20 mm cum 12.1 ₹0.00 ₹0.00
2202 Carriage of Stone aggregate below 40 mm nominal size cum 4.44 ₹0.00 ₹0.00
2267 Carriage of Stone dust cum 1.16 ₹0.00 ₹0.00
2916 Paving Asphalt VG -10 of approved quality tonne 1.85 ₹33,530.00 ₹62,030.50
@ 50kg/10 sqm.
2211 Carriage of Tar bitumen tonne 1.85 ₹0.00 ₹0.00
(B) Labour:
0114 Beldar day 16.67 ₹736.00 ₹12,269.12
for spreading stone metal
0114 Beldar day 5.33 ₹736.00 ₹3,922.88
for hand packing
0114 Beldar day 2.67 ₹736.00 ₹1,965.12
dry rolling
0114 Beldar day 1.33 ₹736.00 ₹978.88
Bajri spreader
0138 Sprayer (for bitumen, tar etc.) day 0.67 ₹816.00 ₹546.72
0114 Beldar day 1.33 ₹736.00 ₹978.88
for spreading key aggregate
0114 Beldar day 6.67 ₹736.00 ₹4,909.12
for spraying bitumen
0114 Beldar day 0.67 ₹736.00 ₹493.12
of power roller
0128 Mate day 1.77 ₹816.00 ₹1,444.32
(C) Machinery :
0001 Hire charges of Coaltar Boiler 900 to 1400 litres day 0.45 ₹900.00 ₹405.00
0003 Hire charges of Diesel Road Roller - 8 to 10 tonne day 0.61 ₹3,350.00 ₹2,043.50
9999 Misc. items as spray nozzle, joint paper, coconut oil, country soap etc. L.S. 351 ₹2.27 ₹796.77

Rate build-up

TOTAL ₹1,31,504.43
Add 1 % Water charges on "W" ₹1,315.04
TOTAL ₹1,32,819.47
Add GST on "X" (multiplying factor 0.2127) ₹28,250.70
TOTAL ₹1,61,070.17
Add 15% CPOH on "Y" ₹24,160.53
TOTAL ₹1,85,230.70
Add Cess @ 1% on "Z" ₹1,852.31
Cost for 370 Sqm. ₹1,87,083.01
Cost per sqm. ₹505.63
Say ₹505.65

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook