DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.31.1.1 rate analysis

Providing and applying tack coat using bitumen emulsion conforming to IS:8887, using emulsion pressure distributer including preparing the surface & cleaning with mechanical broom. With rapid setting bitumen emulsion On W.B.M / W.M.M. @ 0.4kg/sqm

Published rate₹13.45per Sqm
Rate analysis

Providing and applying tack coat using bitumen emulsion conforming to IS:8887, using emulsion pressure distributer including preparing the surface & cleaning with mechanical broom. With rapid setting bitumen emulsion

DSR rate₹13.45per Sqm

On W.B.M / W.M.M. @ 0.4kg/sqm

Item code
16.31.1.1
Sub-head
SH 16 · ROAD WORK
Unit
Sqm
Source row
1477

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 3500 sqm.
MATERIAL
7382 Bitumen emulsion rapid setting (R.S.) confirming to IS : 8887-1995 tonne 1.4 ₹19,893.00 ₹27,850.20
2211 Carriage of Tar bitumen tonne 1.4 ₹0.00 ₹0.00
MACHINERY
0075 Road sweeper (Mechamical Broom) @ 1250 sqm. Per hour. hour 2.8 ₹500.00 ₹1,400.00
0058 Air compressor hour 2.8 ₹250.00 ₹700.00
0061 Emulsion Pressure Distributor @ 1750 sqm per hour hour 2 ₹800.00 ₹1,600.00
LABOUR
0128 Mate day 0.08 ₹816.00 ₹65.28
0114 Beldar day 2 ₹736.00 ₹1,472.00

Rate build-up

TOTAL ₹33,087.48
Add 1 % Water charges on "W" ₹330.87
TOTAL ₹33,418.35
Add GST on "X" (multiplying factor 0.2127) ₹7,108.08
TOTAL ₹40,526.43
Add 15% CPOH on "Y" ₹6,078.96
TOTAL ₹46,605.39
Add Cess @ 1% on "Z" ₹466.05
Cost for 3500 sqm. ₹47,071.44
Cost per Sqm. ₹13.45
Say ₹13.45