DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.31.1.2 rate analysis

Providing and applying tack coat using bitumen emulsion conforming to IS:8887, using emulsion pressure distributer including preparing the surface & cleaning with mechanical broom. With rapid setting bitumen emulsion On bituminous surface @ 0.25kg/sqm

Published rate₹9.20per Sqm
Rate analysis

Providing and applying tack coat using bitumen emulsion conforming to IS:8887, using emulsion pressure distributer including preparing the surface & cleaning with mechanical broom. With rapid setting bitumen emulsion

DSR rate₹9.20per Sqm

On bituminous surface @ 0.25kg/sqm

Item code
16.31.1.2
Sub-head
SH 16 · ROAD WORK
Unit
Sqm
Source row
1477

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 3500 sqm.
MATERIAL
7382 Bitumen emulsion rapid setting (R.S.) confirming to IS : 8887-1995 tonne 0.875 ₹19,893.00 ₹17,406.38
2211 Carriage of Tar bitumen tonne 0.875 ₹0.00 ₹0.00
MACHINERY
0075 Road sweeper (Mechamical Broom) @ 1250 sqm. Per hour. hour 2.8 ₹500.00 ₹1,400.00
0058 Air compressor hour 2.8 ₹250.00 ₹700.00
0061 Emulsion Pressure Distributor @ 1750 sqm per hour hour 2 ₹800.00 ₹1,600.00
LABOUR
0128 Mate day 0.08 ₹816.00 ₹65.28
0114 Beldar day 2 ₹736.00 ₹1,472.00

Rate build-up

TOTAL ₹22,643.66
Add 1 % Water charges on "W" ₹226.44
TOTAL ₹22,870.10
Add GST on "X" (multiplying factor 0.2127) ₹4,864.47
TOTAL ₹27,734.57
Add 15% CPOH on "Y" ₹4,160.19
TOTAL ₹31,894.76
Add Cess @ 1% on "Z" ₹318.95
Cost for 3500 sqm. ₹32,213.71
Cost per Sqm. ₹9.20
Say ₹9.20