DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.30.2 rate analysis

On bituminous surface @ 0.50 Kg / sqm

Published rate₹48.20per Sqm
Rate analysis

On bituminous surface @ 0.50 Kg / sqm

DSR rate₹48.20per Sqm
Item code
16.30.2
Sub-head
SH 16 · ROAD WORK
Unit
Sqm
Source row
1442

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 100 sqm.
MATERIAL
2916 Paving Asphalt VG -10 of approved quality tonne 0.05 ₹33,530.00 ₹1,676.50
2211 Carriage of Tar bitumen tonne 0.05 ₹0.00 ₹0.00
0370 Coal (steam) quintal 0.1 ₹500.00 ₹50.00
2200 Carriage of steam coal tonne 0.01 ₹0.00 ₹0.00
MATERIAL
0364 Wire brush each 0.05 ₹25.00 ₹1.25
(with thick wire)
0365 Soft brush each 0.12 ₹25.00 ₹3.00
9999 Gunny bags L.S. 7.8 ₹2.27 ₹17.71
0007 Hire charges of Coaltar Sprayer day 0.03 ₹400.00 ₹12.00
9999 Sundries L.S. 7.8 ₹2.27 ₹17.71
LABOUR
(a) For cleaning :
0128 Mate day 0.06 ₹816.00 ₹48.96
0114 Beldar day 1.46 ₹736.00 ₹1,074.56
(b) For heating bitumen:
0114 Beldar day 0.19 ₹736.00 ₹139.84
(c) For applying tack coat:
0114 Beldar day 0.47 ₹736.00 ₹345.92

Rate build-up

TOTAL ₹3,387.45
Add 1 % Water charges on "W" ₹33.87
TOTAL ₹3,421.32
Add GST on "X" (multiplying factor 0.2127) ₹727.71
TOTAL ₹4,149.03
Add 15% CPOH on "Y" ₹622.35
TOTAL ₹4,771.38
Add Cess @ 1% on "Z" ₹47.71
Cost for 100 sqm. ₹4,819.09
Cost per Sqm. ₹48.19
Say ₹48.20