DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.18.1 rate analysis

Fencing with angle iron post placed at required distance embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with horizontal lines and two diagonals interwoven with horizontal wires, of barbed wire weighing 9.38 kg per 100 m (minimum), between the two posts fitted and fixed with G.I. staples, turn buckles etc. complete. (Cost of posts, struts, earth work and concrete work to be paid for separately). Payment to be made per metre cost of total length of barbed wire used. With G.I. barbed wire

Published rate₹22.10per m
Rate analysis

Fencing with angle iron post placed at required distance embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with horizontal lines and two diagonals interwoven with horizontal wires, of barbed wire weighing 9.38 kg per 100 m (minimum), between the two posts fitted and fixed with G.I. staples, turn buckles etc. complete. (Cost of posts, struts, earth work and concrete work to be paid for separately). Payment to be made per metre cost of total length of barbed wire used.

DSR rate₹22.10per m

With G.I. barbed wire

Item code
16.18.1
Sub-head
SH 16 · ROAD WORK
Unit
m
Source row
745

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 333.24 metre
MATERIAL
G.I. barbed wire
30x9 = 270.00m
2x10x(12+32)1/2 = 63.24
= 333.24m
333.24m @ 9.38kg/100m =31.26 kg say 0.31 q
1029 Galvanised steel barbed wire quintal 0.31 ₹5,500.00 ₹1,705.00
2314 Carriage of Barbed wire tonne 0.031 ₹0.00 ₹0.00
Supplying and fixing Turn buckle & staple
16.16 Rate as per Item Number 16.16 of SH: Road Work each set 10 ₹274.30 ₹2,743.00
9999 G.I. staples L.S. 49.4 ₹2.27 ₹112.14
Labour for fixing posts in line and fixing and stretching wire:
0123 Mason 1st class day 0.12 ₹897.00 ₹107.64
0124 Mason 2nd class day 0.12 ₹816.00 ₹97.92
0114 Beldar day 0.5 ₹736.00 ₹368.00
0102 Blacksmith 1st class day 0.5 ₹897.00 ₹448.50
0103 Blacksmith 2nd class day 0.5 ₹816.00 ₹408.00

Rate build-up

TOTAL ₹5,990.20
Add 1 % Water charges on "W-A" ₹32.47
TOTAL ₹6,022.67
Add GST on "X-A" (multiplying factor 0.2127) ₹697.59
TOTAL ₹6,720.26
Add 15% CPOH on "Y-A" ₹596.59
TOTAL ₹7,316.85
Add Cess @ 1% on "Z-A" ₹45.74
Cost for 333.24m ₹7,362.59
Cost per m ₹22.09
Say ₹22.10

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook