Rate analysis
Supplying at site Angle iron post & strut of required size including bottom to be split and bent at right angle in opposite direction for 10 cm length and drilling holes upto 10 mm dia. etc. complete.
DSR rate₹125.75as per item analysis
- Item code
- 16.19
- Sub-head
- SH 16 · ROAD WORK
- Unit
- See analysis
- Source row
- 778
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 qunital | |||||
| MATERIAL | |||||
| M.S. angle = 1.00 qtl. | |||||
| Add 5% wastage = 0.05 qtl. | |||||
| Total = =1.05 qtl | |||||
| 1007 | Structurals such as tees,angles channels and R.S. joists | quintal | 1.05 | ₹5,965.00 | ₹6,263.25 |
| 2205 | Carriage of Steel | tonne | 0.105 | ₹0.00 | ₹0.00 |
| LABOUR | |||||
| 0103 | Blacksmith 2nd class | day | 0.75 | ₹816.00 | ₹612.00 |
| 0114 | Beldar | day | 0.5 | ₹736.00 | ₹368.00 |
| For spotting, bending of angle and drilling holes etc. : | |||||
| 0103 | Blacksmith 2nd class | day | 1 | ₹816.00 | ₹816.00 |
| 0114 | Beldar | day | 1 | ₹736.00 | ₹736.00 |
| 9999 | Sundries such as drilling bit etc. | L.S. | 19.76 | ₹2.27 | ₹44.86 |
Rate build-up
| TOTAL | ₹8,840.11 |
| Add 1 % Water charges on "W" | ₹88.40 |
| TOTAL | ₹8,928.51 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,899.09 |
| TOTAL | ₹10,827.60 |
| Add 15% CPOH on "Y" | ₹1,624.14 |
| TOTAL | ₹12,451.74 |
| Add Cess @ 1% on "Z" | ₹124.52 |
| Cost for 1 qunital | ₹12,576.26 |
| Cost of one kg | ₹125.76 |
| Say | ₹125.75 |