DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.17.1 rate analysis

Fencing with R.C.C. post placed at required distance, embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post one side only, provided with horizontal lines and two diagonals of barbed wire weighing 9.38 kg per 100 metres (minimum), between the two posts fitted and fixed with G.I. staples on wooden plugs or G.I. binding wire tied to 6 mm bar nibs fixed while casting the post (cost of R.C.C. posts, struts, earth work and concrete to be paid for separately) :- Payment to be made per metre cost of total length of barbed wire used. With G.I. barbed wire

Published rate₹14.00per m
Rate analysis

Fencing with R.C.C. post placed at required distance, embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post one side only, provided with horizontal lines and two diagonals of barbed wire weighing 9.38 kg per 100 metres (minimum), between the two posts fitted and fixed with G.I. staples on wooden plugs or G.I. binding wire tied to 6 mm bar nibs fixed while casting the post (cost of R.C.C. posts, struts, earth work and concrete to be paid for separately) :- Payment to be made per metre cost of total length of barbed wire used.

DSR rate₹14.00per m

With G.I. barbed wire

Item code
16.17.1
Sub-head
SH 16 · ROAD WORK
Unit
m
Source row
712

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 30m
MATERIAL
G.I. barbed wire
30x9 = 270m +
10x6.32 = 63m
Total = 333m
333m @9.38kg/100m =31.24kg = 0.31q
1029 Galvanised steel barbed wire quintal 0.31 ₹5,500.00 ₹1,705.00
2314 Carriage of Barbed wire tonne 0.03 ₹0.00 ₹0.00
9999 G.I. staples or binding wire L.S. 49.4 ₹2.27 ₹112.14
LABOUR
Labour for fixing costs in line, fixing and stretching wire
0123 Mason 1st class day 0.12 ₹897.00 ₹107.64
0124 Mason 2nd class day 0.12 ₹816.00 ₹97.92
0114 Beldar day 0.5 ₹736.00 ₹368.00
0102 Blacksmith 1st class day 0.5 ₹897.00 ₹448.50
0103 Blacksmith 2nd class day 0.5 ₹816.00 ₹408.00
9999 Sundries L.S. 13.52 ₹2.27 ₹30.69

Rate build-up

TOTAL ₹3,277.89
Add 1 % Water charges on "W" ₹32.78
TOTAL ₹3,310.67
Add GST on "X" (multiplying factor 0.2127) ₹704.18
TOTAL ₹4,014.85
Add 15% CPOH on "Y" ₹602.23
TOTAL ₹4,617.08
Add Cess @ 1% on "Z" ₹46.17
Cost for 333m ₹4,663.25
Cost per m ₹14.00
Say ₹14.00

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook