Fencing with R.C.C. post placed at required distance, embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post one side only, provided with horizontal lines and two diagonals of barbed wire weighing 9.38 kg per 100 metres (minimum), between the two posts fitted and fixed with G.I. staples on wooden plugs or G.I. binding wire tied to 6 mm bar nibs fixed while casting the post (cost of R.C.C. posts, struts, earth work and concrete to be paid for separately) :- Payment to be made per metre cost of total length of barbed wire used.
With G.I. barbed wire
Published rate₹14.00per m
Rate analysis
Fencing with R.C.C. post placed at required distance, embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post one side only, provided with horizontal lines and two diagonals of barbed wire weighing 9.38 kg per 100 metres (minimum), between the two posts fitted and fixed with G.I. staples on wooden plugs or G.I. binding wire tied to 6 mm bar nibs fixed while casting the post (cost of R.C.C. posts, struts, earth work and concrete to be paid for separately) :- Payment to be made per metre cost of total length of barbed wire used.
DSR rate₹14.00per m
With G.I. barbed wire
Item code
16.17.1
Sub-head
SH 16 · ROAD WORK
Unit
m
Source row
712
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Details of cost for 30m
MATERIAL
G.I. barbed wire
30x9 = 270m +
10x6.32 = 63m
Total = 333m
333m @9.38kg/100m =31.24kg = 0.31q
1029
Galvanised steel barbed wire
quintal
0.31
₹5,500.00
₹1,705.00
2314
Carriage of Barbed wire
tonne
0.03
₹0.00
₹0.00
9999
G.I. staples or binding wire
L.S.
49.4
₹2.27
₹112.14
LABOUR
Labour for fixing costs in line, fixing and stretching wire
0123
Mason 1st class
day
0.12
₹897.00
₹107.64
0124
Mason 2nd class
day
0.12
₹816.00
₹97.92
0114
Beldar
day
0.5
₹736.00
₹368.00
0102
Blacksmith 1st class
day
0.5
₹897.00
₹448.50
0103
Blacksmith 2nd class
day
0.5
₹816.00
₹408.00
9999
Sundries
L.S.
13.52
₹2.27
₹30.69
Rate build-up
TOTAL
₹3,277.89
Add 1 % Water charges on "W"
₹32.78
TOTAL
₹3,310.67
Add GST on "X" (multiplying factor 0.2127)
₹704.18
TOTAL
₹4,014.85
Add 15% CPOH on "Y"
₹602.23
TOTAL
₹4,617.08
Add Cess @ 1% on "Z"
₹46.17
Cost for 333m
₹4,663.25
Cost per m
₹14.00
Say
₹14.00