Providing and laying APP (Atactic Polypropylene Polymer) modified prefabricated five layer 3 mm thick water proofing membrane, black finished reinforced with non-woven polyester matt consisting of a coat of bitumen primer for bitumen membrane @ 0.40 litre/sqm by the same membrane manufacture of density at 25°C, 0.87-0.89 kg/ litre and viscocity 70-160 cps. Over the primer coat the layer of membrane shall be laid using Butane Torch and sealing all joints etc, and preparing the surface complete. The vital physical and chemical parameters of the membrane shall be as under : Joint strength in longitudinal and transverse direction at 23°C as 650/ 450N/ 5cm. Tear strength in longitudinal and transverse direction as 300/250N. Softening point of membrane not less than 150°C. Cold flexibility shall be upto -2°C when tested in accordance with ASTM, D - 5147. The laying of membrane shall be got done through the authorised applicator of the manufacturer of membrane :
3 mm thick
Published rate₹560.95DSR 2023
Rate analysis
Providing and laying APP (Atactic Polypropylene Polymer) modified prefabricated five layer 3 mm thick water proofing membrane, black finished reinforced with non-woven polyester matt consisting of a coat of bitumen primer for bitumen membrane @ 0.40 litre/sqm by the same membrane manufacture of density at 25°C, 0.87-0.89 kg/ litre and viscocity 70-160 cps. Over the primer coat the layer of membrane shall be laid using Butane Torch and sealing all joints etc, and preparing the surface complete. The vital physical and chemical parameters of the membrane shall be as under : Joint strength in longitudinal and transverse direction at 23°C as 650/ 450N/ 5cm. Tear strength in longitudinal and transverse direction as 300/250N. Softening point of membrane not less than 150°C. Cold flexibility shall be upto -2°C when tested in accordance with ASTM, D - 5147. The laying of membrane shall be got done through the authorised applicator of the manufacturer of membrane :
DSR rate₹560.95as per item analysis
3 mm thick
Item code
14.91.1
Sub-head
SH 14 · REPAIRS TO BUILDING
Unit
See analysis
Source row
2598
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Detail of cost for 30 sqm
MATERIAL
A.P.P. modified 3 mm thick - 30 sqm
Add 10% for wastage - 3 sqm
Total = 33 sqm
8205
A.P.P. modified 3 mm thick membrance reinforced with polyster matt
sqm
33
₹160.00
₹5,280.00
8206
Bitumen primer for bitumen membrance
litre
12
₹95.00
₹1,140.00
2211
Carriage of Tar bitumen
tonne
0.012
₹0.00
₹0.00
9977
Carriage of bitumen membrance
L.S.
7.8
₹2.27
₹17.71
Fuel
1241
Commercial LPG in cylinder
kg
7
₹106.00
₹742.00
9999
Preparing roof surface, cutting grooves
L.S.
49.53
₹2.27
₹112.43
LABOUR
0159
Skilled torch operator for laying tack
day
2.16
₹897.00
₹1,937.52
0130
Mistry
day
0.18
₹897.00
₹161.46
0114
Beldar
day
3.24
₹736.00
₹2,384.64
9999
Sundries, brushes, bitumen torch etc
L.S.
23.4
₹2.27
₹53.12
Rate build-up
TOTAL
₹11,828.88
Add 1 % Water charges on "W"
₹118.29
TOTAL
₹11,947.17
Add GST on "X" (multiplying factor 0.2127)
₹2,541.16
TOTAL
₹14,488.33
Add 15% CPOH on "Y"
₹2,173.25
TOTAL
₹16,661.58
Add Cess @ 1% on "Z"
₹166.62
Cost for 30 sqm
₹16,828.20
Cost for 1 sqm
₹560.94
Say
₹560.95