DSR 2023 · SH 14 · REPAIRS TO BUILDING

CPWD DSR item 14.90.1 rate analysis

3 mm thick

Published rate₹537.45DSR 2023
Rate analysis

3 mm thick

DSR rate₹537.45as per item analysis
Item code
14.90.1
Sub-head
SH 14 · REPAIRS TO BUILDING
Unit
See analysis
Source row
2568

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 30 sqm
MATERIAL
A.P.P. modified 3 mm thick = 30 sqm
Add 10% for wastage - 3 sqm
Total = 33 sqm
8204 A.P.P. modified 3 mm thick membrance reinforced with glass fibre matt sqm 33 ₹145.00 ₹4,785.00
8206 Bitumen primer for bitumen membrance litre 12 ₹95.00 ₹1,140.00
2211 Carriage of Tar bitumen tonne 0.012 ₹0.00 ₹0.00
9977 Carriage of bitumen membrance L.S. 7.8 ₹2.27 ₹17.71
1241 Commercial LPG in cylinder kg 7 ₹106.00 ₹742.00
9999 Preparing roof surface, cutting grooves L.S. 49.53 ₹2.27 ₹112.43
LABOUR
0159 Skilled torch operator for laying tack day 2.16 ₹897.00 ₹1,937.52
0130 Mistry day 0.18 ₹897.00 ₹161.46
0114 Beldar day 3.24 ₹736.00 ₹2,384.64
9999 Sundries, brushes, bitumen torch etc L.S. 23.4 ₹2.27 ₹53.12

Rate build-up

TOTAL ₹11,333.88
Add 1 % Water charges on "W" ₹113.34
TOTAL ₹11,447.22
Add GST on "X" (multiplying factor 0.2127) ₹2,434.82
TOTAL ₹13,882.04
Add 15% CPOH on "Y" ₹2,082.31
TOTAL ₹15,964.35
Add Cess @ 1% on "Z" ₹159.64
Cost for 30 sqm ₹16,123.99
Cost for 1 sqm ₹537.47
Say ₹537.45