DSR 2023 · SH 14 · REPAIRS TO BUILDING

CPWD DSR item 14.92 rate analysis

Extra for covering top of membrane with Geotextile, 120 gsm non woven, 100% polyester of thickness 1 to 1.25 mm bonded to the membrane with intermittent touch by heating the membrane by Butane Torch as per manufactures recommendation.

Published rate₹88.90DSR 2023
Rate analysis

Extra for covering top of membrane with Geotextile, 120 gsm non woven, 100% polyester of thickness 1 to 1.25 mm bonded to the membrane with intermittent touch by heating the membrane by Butane Torch as per manufactures recommendation.

DSR rate₹88.90as per item analysis
Item code
14.92
Sub-head
SH 14 · REPAIRS TO BUILDING
Unit
See analysis
Source row
2630

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 30 sqm
MATERIAL
Geotextile 120 gsm membrance - 30 sqm
Add 5% for wastage - 1.50 sqm
Total= 31.50 sqm
8207 Geotextile 120 gsm membrance sqm 31.5 ₹27.00 ₹850.50
9977 Carriage of Geotextile L.S. 7.8 ₹2.27 ₹17.71
LABOUR
0159 Skilled torch operator for laying tack day 0.43 ₹897.00 ₹385.71
or fitter 2.16 / 5 = 0.43
0130 Mistry day 0.04 ₹897.00 ₹35.88
0.18 / 5 = 0.04
0114 Beldar day 0.65 ₹736.00 ₹478.40
3.24-5 / 0.65
9999 Sundries, torch, LPG etc L.S. 46.8 ₹2.27 ₹106.24

Rate build-up

TOTAL ₹1,874.44
Add 1 % Water charges on "W" ₹18.74
TOTAL ₹1,893.18
Add GST on "X" (multiplying factor 0.2127) ₹402.68
TOTAL ₹2,295.86
Add 15% CPOH on "Y" ₹344.38
TOTAL ₹2,640.24
Add Cess @ 1% on "Z" ₹26.40
Cost for 30 sqm ₹2,666.64
Cost for 1 sqm ₹88.89
Say ₹88.90

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook