DSR 2023 · SH 14 · REPAIRS TO BUILDING

CPWD DSR item 14.83 rate analysis

Hacking of CC flooring including cleaning for surface etc. complete as per direction of the Engineer-in-Charge.

Published rate₹3.45per sqm
Rate analysis

Hacking of CC flooring including cleaning for surface etc. complete as per direction of the Engineer-in-Charge.

DSR rate₹3.45per sqm
Item code
14.83
Sub-head
SH 14 · REPAIRS TO BUILDING
Unit
sqm
Source row
2378

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 sqm
LABOUR
0114 Beldar day 0.03 ₹736.00 ₹22.08
9999 Sundries L.S. 1 ₹2.27 ₹2.27

Rate build-up

TOTAL ₹24.35
Add 1 % Water charges on "W" ₹0.24
TOTAL ₹24.59
Add GST on "X" (multiplying factor 0.2127) ₹5.23
TOTAL ₹29.82
Add 15% CPOH on "Y" ₹4.47
TOTAL ₹34.29
Add Cess @ 1% on "Z" ₹0.34
Cost of 10 sqm ₹34.63
Cost of 1 sqm ₹3.46
Say ₹3.45