Rate analysis
Dismantling W.C. Pan of all sizes including disposal of dismantled materials i/c malba all complete as per directions of Engineer-in-Charge.
DSR rate₹134.10as per item analysis
- Item code
- 14.82
- Sub-head
- SH 14 · REPAIRS TO BUILDING
- Unit
- See analysis
- Source row
- 2361
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 no. | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 0.125 | ₹736.00 | ₹92.00 |
| 9999 | Sundries | L.S. | 1 | ₹2.27 | ₹2.27 |
Rate build-up
| TOTAL | ₹94.27 |
| Add 1 % Water charges on "W" | ₹0.94 |
| TOTAL | ₹95.21 |
| Add GST on "X" (multiplying factor 0.2127) | ₹20.25 |
| TOTAL | ₹115.46 |
| Add 15% CPOH on "Y" | ₹17.32 |
| TOTAL | ₹132.78 |
| Add Cess @ 1% on "Z" | ₹1.33 |
| Cost of each | ₹134.11 |
| Say | ₹134.10 |