Dismantling 15 to 40 mm dia G.I. pipe including stacking of dismantled pipes (within 50 metres lead) as per direction of Engineer-in-Charge. (a) Internal Work- Exposed on wall

Published rate₹3.25per metre
Rate analysis

Dismantling 15 to 40 mm dia G.I. pipe including stacking of dismantled pipes (within 50 metres lead) as per direction of Engineer-in-Charge. (a) Internal Work- Exposed on wall

DSR rate₹3.25per metre
Item code
14.84
Sub-head
SH 14 · REPAIRS TO BUILDING
Unit
metre
Source row
2396

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 metre
LABOUR
9999 Dismantling of G.I. Pipe and stacking etc. L.S. 10 ₹2.27 ₹22.70

Rate build-up

TOTAL ₹22.70
Add 1 % Water charges on "W" ₹0.23
TOTAL ₹22.93
Add GST on "X" (multiplying factor 0.2127) ₹4.88
TOTAL ₹27.81
Add 15% CPOH on "Y" ₹4.17
TOTAL ₹31.98
Add Cess @ 1% on "Z" ₹0.32
Cost of 10 metres ₹32.30
Cost of 1 metre ₹3.23
Say ₹3.25