DSR 2023 · SH 14 · REPAIRS TO BUILDING

CPWD DSR item 14.8.2 rate analysis

Supplying and fixing new wooden fillets wherever necessary: Hollock wood fillets

Published rate₹70.75DSR 2023
Rate analysis

Supplying and fixing new wooden fillets wherever necessary:

DSR rate₹70.75as per item analysis

Hollock wood fillets

Item code
14.8.2
Sub-head
SH 14 · REPAIRS TO BUILDING
Unit
See analysis
Source row
364

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 metres length
MATERIAL
2466 Hollock wood in scantling 10 cudm 0.115 ₹366.00 ₹42.09
10.00x0.01x0.01 = 1.00 cudm
Add 15% wastage = 0.15 cudm
Total = 1.15 cudm
9999 Nails L.S. 26.91 ₹2.27 ₹61.09
LABOUR
0112 Carpenter 2nd class day 0.25 ₹816.00 ₹204.00
0114 Beldar day 0.25 ₹736.00 ₹184.00
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20

Rate build-up

TOTAL ₹497.38
Add 1 % Water charges on "W" ₹4.97
TOTAL ₹502.35
Add GST on "X" (multiplying factor 0.2127) ₹106.85
TOTAL ₹609.20
Add 15% CPOH on "Y" ₹91.38
TOTAL ₹700.58
Add Cess @ 1% on "Z" ₹7.01
Cost of 10.00 metre ₹707.59
Cost of 1.00 metre ₹70.76
Say ₹70.75