DSR 2023 · SH 14 · REPAIRS TO BUILDING

CPWD DSR item 14.8.1 rate analysis

Supplying and fixing new wooden fillets wherever necessary: 2nd class teak wood fillets

Published rate₹77.70DSR 2023
Rate analysis

Supplying and fixing new wooden fillets wherever necessary:

DSR rate₹77.70as per item analysis

2nd class teak wood fillets

Item code
14.8.1
Sub-head
SH 14 · REPAIRS TO BUILDING
Unit
See analysis
Source row
364

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 metres length
MATERIAL
1190 Second class teak wood in planks 10 cudm 0.115 ₹791.00 ₹90.97
10.00x0.01x0.01 = 1.00 cudm
Add 15% wastage = 0.15 cudm
Total = 1.15 cudm
9999 Nails L.S. 26.91 ₹2.27 ₹61.09
LABOUR
0112 Carpenter 2nd class day 0.25 ₹816.00 ₹204.00
0114 Beldar day 0.25 ₹736.00 ₹184.00
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20

Rate build-up

TOTAL ₹546.26
Add 1 % Water charges on "W" ₹5.46
TOTAL ₹551.72
Add GST on "X" (multiplying factor 0.2127) ₹117.35
TOTAL ₹669.07
Add 15% CPOH on "Y" ₹100.36
TOTAL ₹769.43
Add Cess @ 1% on "Z" ₹7.69
Cost of 10.00 metre ₹777.12
Cost of 1.00 metre ₹77.71
Say ₹77.70