Rate analysis
Renewal of old putty of glass panes (length)
DSR rate₹56.15as per item analysis
- Item code
- 14.9
- Sub-head
- SH 14 · REPAIRS TO BUILDING
- Unit
- See analysis
- Source row
- 415
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 13 metres length | |||||
| MATERIAL | |||||
| 0863 | Putty for wood work | kilogram | 0.68 | ₹32.00 | ₹21.76 |
| 9999 | Nails | L.S. | 7.15 | ₹2.27 | ₹16.23 |
| 9999 | Spirit | L.S. | 2.73 | ₹2.27 | ₹6.20 |
| LABOUR | |||||
| 0112 | Carpenter 2nd class | day | 0.3 | ₹816.00 | ₹244.80 |
| 0114 | Beldar | day | 0.3 | ₹736.00 | ₹220.80 |
| 9999 | Sundries | L.S. | 1.43 | ₹2.27 | ₹3.25 |
Rate build-up
| TOTAL | ₹513.04 |
| Add 1 % Water charges on "W" | ₹5.13 |
| TOTAL | ₹518.17 |
| Add GST on "X" (multiplying factor 0.2127) | ₹110.21 |
| TOTAL | ₹628.38 |
| Add 15% CPOH on "Y" | ₹94.26 |
| TOTAL | ₹722.64 |
| Add Cess @ 1% on "Z" | ₹7.23 |
| Cost of 13.00 metres | ₹729.87 |
| Cost of 1.00 metre | ₹56.14 |
| Say | ₹56.15 |