DSR 2023 · SH 14 · REPAIRS TO BUILDING

CPWD DSR item 14.75A rate analysis

Cleaning of terrace/loft water storage tank (inside surface area) upto 2000 litre capacity at all heights with coconut brushes, duster etc., removal of silt, rubbish from the tank and cleaning the tank with fresh water disinfecting with bleaching powder @ 0.5gm per litre capacity of tank including marking the date of cleaning on the side of tank body with the help of stencil and paint and disposing of malba all complete as per direction of Engineer-in-Charge. (The old date already written on tank should be removed with paint remover or black paint and if date is not written with the stencil or old date is not removed deduction will be made @ Rs. 0.10 per litre) (if during cleaning any GI fittings or ball cock is damaged that is to be repaired by contractor at his own cost and nothing extra will be paid on this account)

Published rate₹0.50per litre
Rate analysis

Cleaning of terrace/loft water storage tank (inside surface area) upto 2000 litre capacity at all heights with coconut brushes, duster etc., removal of silt, rubbish from the tank and cleaning the tank with fresh water disinfecting with bleaching powder @ 0.5gm per litre capacity of tank including marking the date of cleaning on the side of tank body with the help of stencil and paint and disposing of malba all complete as per direction of Engineer-in-Charge. (The old date already written on tank should be removed with paint remover or black paint and if date is not written with the stencil or old date is not removed deduction will be made @ Rs. 0.10 per litre) (if during cleaning any GI fittings or ball cock is damaged that is to be repaired by contractor at his own cost and nothing extra will be paid on this account)

DSR rate₹0.50per litre
Item code
14.75A
Sub-head
SH 14 · REPAIRS TO BUILDING
Unit
litre
Source row
2141

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 tanks
1 tank is of 500 litres capacity i.e. 5000 litres
MATERIAL
1301 Bleaching powder quintal 0.025 ₹1,700.00 ₹42.50
2264 Carriage of Rubbish cum 0.25 ₹185.55 ₹46.39
(asuming 0.040m depth of silt)
9999 Marking with paint i/c removal of existing markings L.S. 30 ₹2.27 ₹68.10
LABOUR
0117 Assistant Fitter or 2nd class Fitter day 1 ₹816.00 ₹816.00
for opening ball cock wheel valve and other fittings
0114 Beldar day 1 ₹736.00 ₹736.00
for cleaning disinfecting etc

Rate build-up

TOTAL ₹1,708.99
Add 1 % Water charges on "W" ₹17.09
TOTAL ₹1,726.08
Add GST on "X" (multiplying factor 0.2127) ₹367.14
TOTAL ₹2,093.22
Add 15% CPOH on "Y" ₹313.98
TOTAL ₹2,407.20
Add Cess @ 1% on "Z" ₹24.07
Cost of 5000 litre ₹2,431.27
Cost of 1 litre ₹0.49
Say ₹0.50

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook