Rate analysis
Cleaning and desilting of gully trap chamber, including removal of rubbish mixed with earth etc. and disposal of same, all as per the direction of Engineer-in-charge.
DSR rate₹108.30as per item analysis
- Item code
- 14.76
- Sub-head
- SH 14 · REPAIRS TO BUILDING
- Unit
- See analysis
- Source row
- 2167
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 Nos. | |||||
| LABOUR | |||||
| 0129 | Sewerman | day | 1 | ₹736.00 | ₹736.00 |
| 9999 | T & P Bamboo, bucket, whell barrow etc. | L.S. | 11.2 | ₹2.27 | ₹25.42 |
Rate build-up
| TOTAL | ₹761.42 |
| Add 1 % Water charges on "W" | ₹7.61 |
| TOTAL | ₹769.03 |
| Add GST on "X" (multiplying factor 0.2127) | ₹163.57 |
| TOTAL | ₹932.60 |
| Add 15% CPOH on "Y" | ₹139.89 |
| TOTAL | ₹1,072.49 |
| Add Cess @ 1% on "Z" | ₹10.72 |
| Cost of 10 nos | ₹1,083.21 |
| Cost of each | ₹108.32 |
| Say | ₹108.30 |