DSR 2023 · SH 14 · REPAIRS TO BUILDING

CPWD DSR item 14.76 rate analysis

Cleaning and desilting of gully trap chamber, including removal of rubbish mixed with earth etc. and disposal of same, all as per the direction of Engineer-in-charge.

Published rate₹108.30DSR 2023
Rate analysis

Cleaning and desilting of gully trap chamber, including removal of rubbish mixed with earth etc. and disposal of same, all as per the direction of Engineer-in-charge.

DSR rate₹108.30as per item analysis
Item code
14.76
Sub-head
SH 14 · REPAIRS TO BUILDING
Unit
See analysis
Source row
2167

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 Nos.
LABOUR
0129 Sewerman day 1 ₹736.00 ₹736.00
9999 T & P Bamboo, bucket, whell barrow etc. L.S. 11.2 ₹2.27 ₹25.42

Rate build-up

TOTAL ₹761.42
Add 1 % Water charges on "W" ₹7.61
TOTAL ₹769.03
Add GST on "X" (multiplying factor 0.2127) ₹163.57
TOTAL ₹932.60
Add 15% CPOH on "Y" ₹139.89
TOTAL ₹1,072.49
Add Cess @ 1% on "Z" ₹10.72
Cost of 10 nos ₹1,083.21
Cost of each ₹108.32
Say ₹108.30