Rate analysis
Repair to plaster of thickness 12mm to 20 mm in patches of area 2.5 sqm and under, including cutting the patch in proper shape, raking out joints and preparing plastering the wall surface with white cement based polymer modified self curing mortar, including disposal of rubbish, all complete as per the direction of Engineer-In-Charge.
DSR rate₹670.95per sqm
- Item code
- 14.75
- Sub-head
- SH 14 · REPAIRS TO BUILDING
- Unit
- sqm
- Source row
- 2117
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 sqm | |||||
| MATERIAL | |||||
| 0772 | White cement based polymer modified self curing compound in powder form | kg | 125 | ₹18.00 | ₹2,250.00 |
| i/c 2% wastage | |||||
| 9977 | Carriage of white cement based polymer modified self curing compound in powder form | L.S. | 21.1 | ₹2.27 | ₹47.90 |
| LABOUR | |||||
| 0155 | Mason (average) | day | 1.21 | ₹857.00 | ₹1,036.97 |
| 0114 | Beldar | day | 0.54 | ₹736.00 | ₹397.44 |
| 0115 | Coolie | day | 1.29 | ₹736.00 | ₹949.44 |
| 9999 | Scaffolding and sunderies | L.S. | 15.21 | ₹2.27 | ₹34.53 |
Rate build-up
| TOTAL | ₹4,716.28 |
| Add 1 % Water charges on "W" | ₹47.16 |
| TOTAL | ₹4,763.44 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,013.18 |
| TOTAL | ₹5,776.62 |
| Add 15% CPOH on "Y" | ₹866.49 |
| TOTAL | ₹6,643.11 |
| Add Cess @ 1% on "Z" | ₹66.43 |
| Cost of 10 sqm | ₹6,709.54 |
| Cost of 1 sqm | ₹670.95 |
| Say | ₹670.95 |