DSR 2023 · SH 14 · REPAIRS TO BUILDING

CPWD DSR item 14.19 rate analysis

Taking out wind ties from roof including cutting out rusted bolts, nuts etc. and removing materials to any distance within compound and stacking.

Published rate₹5.40DSR 2023
Rate analysis

Taking out wind ties from roof including cutting out rusted bolts, nuts etc. and removing materials to any distance within compound and stacking.

DSR rate₹5.40as per item analysis
Item code
14.19
Sub-head
SH 14 · REPAIRS TO BUILDING
Unit
See analysis
Source row
881

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 30 mtrs of weight 63 kgs
M.S. Flats 40x6mm @ 1.9kg./m = 30x1.9 = 57 kg. (A)
J' hook bolts @ 30cm centre to centre = 101 Nos. x 0.15 m = 15.15 m @ 0.40kg./ m = 6.06kg (B)
Total (A+B) = 63.06 kg Say 63 kg
LABOUR
0103 Blacksmith 2nd class day 0.09 ₹816.00 ₹73.44
0100 Bandhani day 0.06 ₹816.00 ₹48.96
0114 Beldar day 0.16 ₹736.00 ₹117.76

Rate build-up

TOTAL ₹240.16
Add 1 % Water charges on "W" ₹2.40
TOTAL ₹242.56
Add GST on "X" (multiplying factor 0.2127) ₹51.59
TOTAL ₹294.15
Add 15% CPOH on "Y" ₹44.12
TOTAL ₹338.27
Add Cess @ 1% on "Z" ₹3.38
Cost for 63 kg. ₹341.65
Cost of 1.00 kg ₹5.42
Say ₹5.40