Rate analysis
Taking out wind ties from roof including cutting out rusted bolts, nuts etc. and removing materials to any distance within compound and stacking.
DSR rate₹5.40as per item analysis
- Item code
- 14.19
- Sub-head
- SH 14 · REPAIRS TO BUILDING
- Unit
- See analysis
- Source row
- 881
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 30 mtrs of weight 63 kgs | |||||
| M.S. Flats 40x6mm @ 1.9kg./m = 30x1.9 = 57 kg. (A) | |||||
| J' hook bolts @ 30cm centre to centre = 101 Nos. x 0.15 m = 15.15 m @ 0.40kg./ m = 6.06kg (B) | |||||
| Total (A+B) = 63.06 kg Say 63 kg | |||||
| LABOUR | |||||
| 0103 | Blacksmith 2nd class | day | 0.09 | ₹816.00 | ₹73.44 |
| 0100 | Bandhani | day | 0.06 | ₹816.00 | ₹48.96 |
| 0114 | Beldar | day | 0.16 | ₹736.00 | ₹117.76 |
Rate build-up
| TOTAL | ₹240.16 |
| Add 1 % Water charges on "W" | ₹2.40 |
| TOTAL | ₹242.56 |
| Add GST on "X" (multiplying factor 0.2127) | ₹51.59 |
| TOTAL | ₹294.15 |
| Add 15% CPOH on "Y" | ₹44.12 |
| TOTAL | ₹338.27 |
| Add Cess @ 1% on "Z" | ₹3.38 |
| Cost for 63 kg. | ₹341.65 |
| Cost of 1.00 kg | ₹5.42 |
| Say | ₹5.40 |