DSR 2023 · SH 13 · FINISHING

CPWD DSR item 13.33.2 rate analysis

Pointing on stone work with cement mortar 1:3 (1 cement : 3 fine sand) : Raised and cut pointing

Published rate₹701.05DSR 2023
Rate analysis

Pointing on stone work with cement mortar 1:3 (1 cement : 3 fine sand) :

DSR rate₹701.05as per item analysis

Raised and cut pointing

Item code
13.33.2
Sub-head
SH 13 · FINISHING
Unit
See analysis
Source row
1279

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 sqm
MATERIAL
Cement mortar 1 : 3 (1 cement : 3 fine sand)
3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.038 ₹4,379.05 ₹166.40
9999 Sundries L.S. 7.15 ₹2.27 ₹16.23
LABOUR
0155 Mason (average) day 2 ₹857.00 ₹1,714.00
0115 Coolie day 2.96 ₹736.00 ₹2,178.56
0101 Bhisti day 1 ₹816.00 ₹816.00
9999 Scaffolding and racking out joints including sundries L.S. 16.12 ₹2.27 ₹36.59

Rate build-up

TOTAL ₹4,927.78
Add 1 % Water charges on "W" ₹49.28
TOTAL ₹4,977.06
Add GST on "X" (multiplying factor 0.2127) ₹1,058.62
TOTAL ₹6,035.68
Add 15% CPOH on "Y" ₹905.35
TOTAL ₹6,941.03
Add Cess @ 1% on "Z" ₹69.41
Cost of 10.00 sqm ₹7,010.44
Cost of 1.00 sqm ₹701.04
Say ₹701.05