DSR 2023 · SH 13 · FINISHING

CPWD DSR item 13.34 rate analysis

Raised and cut pointing on stone work in white cement mortar 1:3 (1 white cement : 3 marble dust).

Published rate₹716.95DSR 2023
Rate analysis

Raised and cut pointing on stone work in white cement mortar 1:3 (1 white cement : 3 marble dust).

DSR rate₹716.95as per item analysis
Item code
13.34
Sub-head
SH 13 · FINISHING
Unit
See analysis
Source row
1328

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 sqm
MATERIAL
White Cement mortar 1:3 (1 white cement : 3 marble dust)
3.16 Rate as per Item Number 3.16 of SH: Mortars cum 0.038 ₹7,318.50 ₹278.10
9999 Sundries L.S. 7.15 ₹2.27 ₹16.23
LABOUR
0155 Mason (average) day 2 ₹857.00 ₹1,714.00
0115 Coolie day 2.96 ₹736.00 ₹2,178.56
0101 Bhisti day 1 ₹816.00 ₹816.00
9999 Scaffolding and racking out joints including sundries L.S. 16.12 ₹2.27 ₹36.59

Rate build-up

TOTAL ₹5,039.48
Add 1 % Water charges on "W" ₹50.39
TOTAL ₹5,089.87
Add GST on "X" (multiplying factor 0.2127) ₹1,082.62
TOTAL ₹6,172.49
Add 15% CPOH on "Y" ₹925.87
TOTAL ₹7,098.36
Add Cess @ 1% on "Z" ₹70.98
Cost of 10.00 sqm ₹7,169.34
Cost of 1.00 sqm ₹716.93
Say ₹716.95