DSR 2023 · SH 13 · FINISHING

CPWD DSR item 13.33.1 rate analysis

Pointing on stone work with cement mortar 1:3 (1 cement : 3 fine sand) : Flush/ Ruled pointing

Published rate₹385.40DSR 2023
Rate analysis

Pointing on stone work with cement mortar 1:3 (1 cement : 3 fine sand) :

DSR rate₹385.40as per item analysis

Flush/ Ruled pointing

Item code
13.33.1
Sub-head
SH 13 · FINISHING
Unit
See analysis
Source row
1279

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 sqm
MATERIAL
Cement mortar 1 : 3 (1 cement : 3 fine sand)
3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.023 ₹4,379.05 ₹100.72
9999 Sundries L.S. 7.15 ₹2.27 ₹16.23
LABOUR
0155 Mason (average) day 0.92 ₹857.00 ₹788.44
0115 Coolie day 1.37 ₹736.00 ₹1,008.32
0101 Bhisti day 0.93 ₹816.00 ₹758.88
9999 Scaffolding and racking out joints including sundries L.S. 16.12 ₹2.27 ₹36.59

Rate build-up

TOTAL ₹2,709.18
Add 1 % Water charges on "W" ₹27.09
TOTAL ₹2,736.27
Add GST on "X" (multiplying factor 0.2127) ₹582.00
TOTAL ₹3,318.27
Add 15% CPOH on "Y" ₹497.74
TOTAL ₹3,816.01
Add Cess @ 1% on "Z" ₹38.16
Cost of 10.00 sqm ₹3,854.17
Cost of 1.00 sqm ₹385.42
Say ₹385.40

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook