DSR 2023 · SH 13 · FINISHING

CPWD DSR item 13.25.2 rate analysis

Extra for plastering: Groined ceiling

Published rate₹192.30DSR 2023
Rate analysis

Extra for plastering:

DSR rate₹192.30as per item analysis

Groined ceiling

Item code
13.25.2
Sub-head
SH 13 · FINISHING
Unit
See analysis
Source row
892

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 sqm
LABOUR
0155 Mason (average) day 0.8 ₹857.00 ₹685.60
0114 Beldar day 0.8 ₹736.00 ₹588.80
9999 Sundries L.S. 34.06 ₹2.27 ₹77.32

Rate build-up

TOTAL ₹1,351.72
Add 1 % Water charges on "W" ₹13.52
TOTAL ₹1,365.24
Add GST on "X" (multiplying factor 0.2127) ₹290.39
TOTAL ₹1,655.63
Add 15% CPOH on "Y" ₹248.34
TOTAL ₹1,903.97
Add Cess @ 1% on "Z" ₹19.04
Cost of 10.00 sqm ₹1,923.01
Cost of 1.00 sqm ₹192.30
Say ₹192.30

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.