CPWD DSR item 13.25.3 rate analysis

Extra for plastering: Flewing soffits

Published rate₹117.65DSR 2023
Rate analysis

Extra for plastering:

DSR rate₹117.65as per item analysis

Flewing soffits

Item code
13.25.3
Sub-head
SH 13 · FINISHING
Unit
See analysis
Source row
892

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 sqm
LABOUR
0155 Mason (average) day 0.5 ₹857.00 ₹428.50
0114 Beldar day 0.5 ₹736.00 ₹368.00
9999 Sundries L.S. 13.39 ₹2.27 ₹30.40

Rate build-up

TOTAL ₹826.90
Add 1 % Water charges on "W" ₹8.27
TOTAL ₹835.17
Add GST on "X" (multiplying factor 0.2127) ₹177.64
TOTAL ₹1,012.81
Add 15% CPOH on "Y" ₹151.92
TOTAL ₹1,164.73
Add Cess @ 1% on "Z" ₹11.65
Cost of 10.00 sqm ₹1,176.38
Cost of 1.00 sqm ₹117.64
Say ₹117.65

Use this rate in the interactive workbook