Rate analysis
Extra for plastering:
DSR rate₹177.60as per item analysis
Spherical ceiling
- Item code
- 13.25.1
- Sub-head
- SH 13 · FINISHING
- Unit
- See analysis
- Source row
- 892
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 10 sqm | |||||
| LABOUR | |||||
| 0155 | Mason (average) | day | 0.75 | ₹857.00 | ₹642.75 |
| 0114 | Beldar | day | 0.74 | ₹736.00 | ₹544.64 |
| 9999 | Sundries | L.S. | 26.91 | ₹2.27 | ₹61.09 |
Rate build-up
| TOTAL | ₹1,248.48 |
| Add 1 % Water charges on "W" | ₹12.48 |
| TOTAL | ₹1,260.96 |
| Add GST on "X" (multiplying factor 0.2127) | ₹268.21 |
| TOTAL | ₹1,529.17 |
| Add 15% CPOH on "Y" | ₹229.38 |
| TOTAL | ₹1,758.55 |
| Add Cess @ 1% on "Z" | ₹17.59 |
| Cost of 10.00 sqm | ₹1,776.14 |
| Cost of 1.00 sqm | ₹177.61 |