DSR 2023 · SH 13 · FINISHING

CPWD DSR item 13.109.2 rate analysis

Finishing walls with water proofing cement paint of required shade : Old work (one or more coats @ 2.20 kg/10 sqm) complete.

Published rate₹75.80DSR 2023
Rate analysis

Finishing walls with water proofing cement paint of required shade :

DSR rate₹75.80as per item analysis

Old work (one or more coats @ 2.20 kg/10 sqm) complete.

Item code
13.109.2
Sub-head
SH 13 · FINISHING
Unit
See analysis
Source row
3620

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 sqm
MATERIAL
0851 Water proofing cement paint kilogram 2.2 ₹41.00 ₹90.20
9977 Carriage of material L.S. 1.1 ₹2.27 ₹2.50
LABOUR
0131 Painter day 0.35 ₹816.00 ₹285.60
0115 Coolie day 0.12 ₹736.00 ₹88.32
0101 Bhisti day 0.05 ₹816.00 ₹40.80
9999 Brushes, sand paper etc L.S. 3.15 ₹2.27 ₹7.15
9999 Sundries L.S. 8.06 ₹2.27 ₹18.30

Rate build-up

TOTAL ₹532.87
Add 1 % Water charges on "W" ₹5.33
TOTAL ₹538.20
Add GST on "X" (multiplying factor 0.2127) ₹114.48
TOTAL ₹652.68
Add 15% CPOH on "Y" ₹97.90
TOTAL ₹750.58
Add Cess @ 1% on "Z" ₹7.51
Cost of 10.00 sqm ₹758.09
Cost of 1.00 sqm ₹75.81
Say ₹75.80

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook