Rate analysis
Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete:
DSR rate₹428.50as per item analysis
Corrugated apron pieces
- Item code
- 12.13.1
- Sub-head
- SH 12 · ROOFING
- Unit
- See analysis
- Source row
- 747
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details for shed of 20.2 metres completed length | |||||
| MATERIAL | |||||
| Corrugated appron pieces of 1.12 metre length = 20 nos.+ | |||||
| Add 5% wastage = 1.0 No. | |||||
| Total = 21 nos.x 1.12=23.52 metre | |||||
| 0228 | Fibre reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated appron piece. | metre | 23.52 | ₹220.00 | ₹5,174.40 |
| 9977 | Carriage of appron pieces. (The appron pieces are to be fixed with the same hooks as the sheets) | L.S. | 3.25 | ₹2.27 | ₹7.38 |
| 9999 | Sundries | L.S. | 3.25 | ₹2.27 | ₹7.38 |
| LABOUR | |||||
| 0130 | Mistry | day | 0.07 | ₹897.00 | ₹62.79 |
| 0112 | Carpenter 2nd class | day | 0.28 | ₹816.00 | ₹228.48 |
| 0114 | Beldar | day | 0.82 | ₹736.00 | ₹603.52 |
Rate build-up
| TOTAL | ₹6,083.95 |
| Add 1 % Water charges on "W" | ₹60.84 |
| TOTAL | ₹6,144.79 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,307.00 |
| TOTAL | ₹7,451.79 |
| Add 15% CPOH on "Y" | ₹1,117.77 |
| TOTAL | ₹8,569.56 |
| Add Cess @ 1% on "Z" | ₹85.70 |
| Cost of 20.20 metre | ₹8,655.26 |
| Cost of 1.00 metre | ₹428.48 |
| Say | ₹428.50 |