Rate analysis
Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete:
DSR rate₹345.05as per item analysis
Eave's filler pieces
- Item code
- 12.13.2
- Sub-head
- SH 12 · ROOFING
- Unit
- See analysis
- Source row
- 747
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of eaves filler for a shed of 20.2 metres complete length | |||||
| MATERIAL | |||||
| Eaves filler pieces of 0.16 metres length = 20 nos.+ | |||||
| Add 5% wastage = 1.0 No. | |||||
| Total = 21 nos. | |||||
| 0229 | Fibre reinforced by organic fibres and/or inorganic synthetic fibres cement eaves filler piece. | each | 21 | ₹190.00 | ₹3,990.00 |
| 9999 | The eaves filler pieces are to be fixed with the same hooks as the sheets | L.S. | 3.25 | ₹2.27 | ₹7.38 |
| 9999 | Sundries | L.S. | 3.25 | ₹2.27 | ₹7.38 |
| LABOUR | |||||
| 0130 | Mistry | day | 0.07 | ₹897.00 | ₹62.79 |
| 0112 | Carpenter 2nd class | day | 0.28 | ₹816.00 | ₹228.48 |
| 0114 | Beldar | day | 0.82 | ₹736.00 | ₹603.52 |
Rate build-up
| TOTAL | ₹4,899.55 |
| Add 1 % Water charges on "W" | ₹49.00 |
| TOTAL | ₹4,948.55 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,052.56 |
| TOTAL | ₹6,001.11 |
| Add 15% CPOH on "Y" | ₹900.17 |
| TOTAL | ₹6,901.28 |
| Add Cess @ 1% on "Z" | ₹69.01 |
| Cost of 20.20 metres | ₹6,970.29 |
| Cost of 1.00 metre | ₹345.06 |
| Say | ₹345.05 |