Rate analysis
Providing and fixing ridges and hips in fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing with suitable fixing accessories or self drilling fastener and EPDM washer etc. complete.
DSR rate₹521.85as per item analysis
Unserrated adjustable hips
- Item code
- 12.12.4
- Sub-head
- SH 12 · ROOFING
- Unit
- See analysis
- Source row
- 633
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for a shed with hip as 20.2 metres Unserrated adjustable hips | |||||
| Consider a shed with hip as 20.2 metres | |||||
| No. of hi pieces required = 19 pairs | |||||
| Length of each pair 1.22 metres | |||||
| Add 5 % wastage = 0.95 pairs | |||||
| = 19.95 pairs x 1.22 = 24.339 metre | |||||
| 0227 | Fibre reinforced by organic fibres and/or inorganic synthetic fibres cement unserrated adjustable ridge for hips. | metre | 24.339 | ₹230.00 | ₹5,597.97 |
| 9977 | Carriage | L.S. | 6.76 | ₹2.27 | ₹15.35 |
| 9999 | Sundries | L.S. | 6.63 | ₹2.27 | ₹15.05 |
| LABOUR | |||||
| 0130 | Mistry | day | 0.14 | ₹897.00 | ₹125.58 |
| 0112 | Carpenter 2nd class | day | 0.55 | ₹816.00 | ₹448.80 |
| 0114 | Beldar | day | 1.64 | ₹736.00 | ₹1,207.04 |
Rate build-up
| TOTAL | ₹7,409.79 |
| Add 1 % Water charges on "W" | ₹74.10 |
| TOTAL | ₹7,483.89 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,591.82 |
| TOTAL | ₹9,075.71 |
| Add 15% CPOH on "Y" | ₹1,361.36 |
| TOTAL | ₹10,437.07 |
| Add Cess @ 1% on "Z" | ₹104.37 |
| Cost of 20.20 metre | ₹10,541.44 |
| Cost of 1.00 metre | ₹521.85 |
| Say | ₹521.85 |